Message type: E = Error
Message class: /SAPAPO/SNP -
Message number: 431
Message text: Cal. from planning cal. &1 for production at loc. &2 is diff. frm res. &3
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/SNP431
- Cal. from planning cal. &1 for production at loc. &2 is diff. frm res. &3 ?The SAP error message
/SAPAPO/SNP431
typically occurs in the context of Advanced Planning and Optimization (APO) when there is a discrepancy between the planning calendar and the resource calendar for a specific location and resource. This error indicates that the planning calendar used for production does not match the calendar defined for the resource.Cause:
- Mismatch in Calendars: The planning calendar for the production order is different from the resource calendar defined for the specific location and resource.
- Resource Availability: The resource may not be available for the entire duration of the planning calendar, leading to scheduling conflicts.
- Incorrect Configuration: There may be incorrect settings in the configuration of the planning area or resource settings.
Solution:
Check Calendars:
- Verify the planning calendar assigned to the production order and the resource calendar assigned to the resource at the specified location.
- Ensure that both calendars are aligned in terms of working days and hours.
Adjust Resource Settings:
- If the resource calendar is not set up correctly, adjust the resource's availability in the resource master data.
- Ensure that the resource is available during the planned production times.
Modify Planning Calendar:
- If necessary, modify the planning calendar to match the resource calendar or vice versa, depending on the business requirements.
Re-schedule Production Orders:
- After making the necessary adjustments, re-schedule the production orders to ensure they align with the updated calendars.
Consult Documentation:
- Review SAP documentation or consult with your SAP Basis or APO consultant for specific configuration settings that may need to be adjusted.
Related Information:
/SAPAPO/MC90
(for planning book) or /SAPAPO/RES01
(for resource overview) to check and modify the relevant settings.By following these steps, you should be able to resolve the error and ensure that the planning and resource calendars are aligned for successful production scheduling.
Get instant SAP help. Start your 7-day free trial now.
/SAPAPO/SNP430
Planning calendar (time stream) &1 is not set to UTC timezone
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
/SAPAPO/SNP429
Horizon for planning calendar &1 at location &2 is not 00:00:00-24:00:00
What causes this issue? The planning calendar (timestream) &V1& that you specified at location &V2&, has not been set as 00:00:00-24:...
/SAPAPO/SNP432
Cal. from planning cal. &1 for shipment at loc. &2 is diffnt from res. &3
What causes this issue? The calendar from the planning calendar (timestream) &V1& that you specified for shipment at location &V2&, i...
/SAPAPO/SNP433
Cal. from planning cal. &1 for warehouse at loc. &2 is diffnt frm res. &3
What causes this issue? The calendar from the planning calendar (timestream) &V1& that you specified for the warehouse at location &V2&am...