Do you have any question about this error?
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 730
Message text: Resource assignments to group of activities & not supported
You have assigned resources to collective activities in Microsoft
Project (R). The SAP Project System does not recognize collective
activities.
The resource assignment to collective activites will be ignored during
upload.
Collective activities are only used during upload to assign activities
to standard networks.
Error message extract from SAP system. Copyright SAP SE.
PJ730
- Resource assignments to group of activities & not supported ?The SAP error message PJ730, which states "Resource assignments to group of activities are not supported," typically occurs in the context of project management within SAP, particularly when dealing with project structures and resource assignments.
Cause:
This error usually arises when you attempt to assign resources to a group of activities (like a project or a work breakdown structure) rather than to individual activities. In SAP, resource assignments are expected to be made at the activity level, not at the group level. This is because resource planning and allocation need to be specific to each activity to ensure accurate tracking and management.
Solution:
To resolve this error, you should follow these steps:
Check Resource Assignment: Ensure that you are trying to assign resources to individual activities rather than to a group of activities.
Navigate to the Correct Activity: Go to the specific activity within the project structure where you want to assign the resource.
Assign Resources Individually: Use the appropriate transaction (like CJ20N for Project Builder) to assign resources directly to the individual activities.
Review Project Structure: If you are working with a project structure that includes groups, ensure that you are aware of which activities belong to those groups and focus on the individual activities for resource assignments.
Consult Documentation: If you are unsure about the process, refer to SAP documentation or help resources related to project management and resource planning.
Related Information:
By following these steps, you should be able to resolve the PJ730 error and successfully assign resources to the appropriate activities in your SAP project.
Get instant SAP help. Start your 7-day free trial now.
PJ720
Milestone indicator & not valid (Please check)
What causes this issue? The MPX file contains a milestone that is not defined in the SAP System.System Response The milestone indicator will be igno...
PJ710
Control key & not valid (Please check)
What causes this issue? The MPX file contains a control key that is not defined in the SAP System.System Response The control key will be ignored du...
PJ740
W: Objects not entered could be referenced: BDC may stop
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PJ750
W: Resources not entered could be referenced: BDC may stop
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.