Do you have any question about this error?
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 710
Message text: Control key & not valid (Please check)
The MPX file contains a control key that is not defined in the SAP
System.
The control key will be ignored during upload.
Error message extract from SAP system. Copyright SAP SE.
PJ710
- Control key & not valid (Please check) ?The SAP error message PJ710, which states "Control key & not valid (Please check)," typically occurs in the context of project management or project system (PS) modules when a user attempts to create or modify a project-related object (like a network, activity, or WBS element) using an invalid control key.
Cause:
- Invalid Control Key: The control key specified does not exist in the system or is not defined for the type of operation you are trying to perform.
- Configuration Issues: The control key may not be properly configured in the system, or it may not be assigned to the relevant project type or activity type.
- Authorization Issues: The user may not have the necessary authorizations to use the specified control key.
- Data Entry Error: There may be a typographical error in the control key entered.
Solution:
Check Control Key: Verify that the control key you are using is valid. You can do this by navigating to the configuration settings in SAP:
- Go to transaction code
OPKP
orOPL8
to check the control keys defined in the system.- Ensure that the control key is active and assigned to the correct project type or activity type.
Correct Configuration: If the control key is not valid, you may need to create or modify it:
- Use transaction code
OPL8
to create or change control keys.- Ensure that the control key is configured correctly for the intended use (e.g., for network activities, WBS elements, etc.).
Check Authorizations: Ensure that the user has the necessary authorizations to use the control key. This can be checked with the help of your SAP security team.
Data Entry Verification: Double-check the input for any typographical errors. Make sure that the control key is entered correctly.
Consult Documentation: If you are unsure about the control key's purpose or configuration, refer to SAP documentation or consult with a functional consultant who specializes in the Project System module.
Related Information:
CJ20N
(Project Builder), CJ02
(Change Project), and CJ01
(Create Project) for managing projects.If the issue persists after following these steps, it may be beneficial to reach out to your SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
PJ700
PC file not found
What causes this issue? The PC file that you maintained for the upload was not found.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJE...
PJ690
Duration "&" is not in a valid MPX unit (Please correct)
What causes this issue? The unit for time has an invalid MPX format.System Response The system issues an error message and will not allow you to con...
PJ720
Milestone indicator & not valid (Please check)
What causes this issue? The MPX file contains a milestone that is not defined in the SAP System.System Response The milestone indicator will be igno...
PJ730
Resource assignments to group of activities & not supported
What causes this issue? You have assigned resources to collective activities in Microsoft Project (R). The SAP Project System does not recognize coll...