Message type: E = Error
Message class: O1 - IS-Oil : Message pool exchanges
Message number: 027
Message text: Please check last sched.date & against breakdown indicator
It could be that the last scheduling period does not match the
<DS:DE.BISDAT>"valid-to" date</> and the
<DS:DE.OIA_ENTLU>breakdown indicator</>,
which means that the last period has a date which is too early. A
subsequent scheduling period may have been deleted manually or the
validity period was changed after the quantity schedule was created.
&SYSTEM_RESPONSE& / &SYSTEM_MESSAGE&
This message is controlled by Table T160M (System Messages). If the
type does not have an initial value (empty), it appears as a warning
message.
Check the "valid-to" date in the quantity schedule.
Check the breakdown indicator.
Check the schedule lines (last schedule line).
Insert a scheduling period after the last scheduling period.
Error message extract from SAP system. Copyright SAP SE.
O1027
- Please check last sched.date & against breakdown indicator ?The SAP error message O1027, which states "Please check last sched.date & against breakdown indicator," typically occurs in the context of maintenance planning and scheduling within the SAP system, particularly in the Plant Maintenance (PM) module. This error indicates that there is an issue with the scheduling of maintenance tasks, specifically related to the breakdown indicator and the last scheduled date.
Cause: Breakdown Indicator: The breakdown indicator is used to determine whether a maintenance task is planned as a breakdown maintenance or a preventive maintenance. If the indicator is set incorrectly or if there is a mismatch between the last scheduled date and the breakdown indicator, this error can occur. Last Scheduled Date: The last scheduled date may not align with the expected maintenance schedule. If the date is in the past or not properly updated, it can trigger this error.
Configuration Issues: There may be configuration issues in the maintenance planning settings that
Get instant SAP help. Sign up for our Free Essentials Plan.
O1026
First sched.date does not match fact.day "from day" &, check
What causes this issue? "Valid from" date in quantity schedule does not match the first schedule line in the quantity schedule. &SYSTEM...
O1025
QS target qty.: & & - total referenced: & (&)
What causes this issue? Several <DS:GLOS.release order>call-off</> items with the same contract item reference. The SUM of the <DS:GLO...
O1028
GR qty.by & & > avail., (QS period: & &)
What causes this issue? <DS:GLOS.goods receipt>Goods receipt</> quantity exceeds the available quantity in the quantity schedule, for th...
O1029
Del.qty.by & & > avail., (QS period: & &)
What causes this issue? The delivered quantity exceeds the available quantity in the quantity schedule for this item, the <DS:DE.UEBTK_V>unlimi...
Click on this link to search all SAP messages.