Message type: E = Error
Message class: KJ - Cost Object Controlling for Make-to-Order Production
Message number: 314
Message text: Create a cost element for revenue in excess of billings
If you are using the POC method to perform results analysis, the system
computes the calculated revenue by multiplying the percentage of
completion by the planned revenue. If the calculated revenue exceeds the
actual revenue, the system creates revenue in excess of billings.
The revenue in excess of billings is written under a results analysis
cost element.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Create a results analysis cost element for the revenue in excess of
billings.
Go into Customizing and enter the results analysis cost element in the
results analysis version.
Error message extract from SAP system. Copyright SAP SE.
KJ314
- Create a cost element for revenue in excess of billings ?The SAP error message KJ314, "Create a cost element for revenue in excess of billings," typically occurs in the context of project accounting or internal orders when there is a discrepancy between the revenue recognized and the billings made. This error indicates that there is revenue that has been recognized in the system that exceeds the amount that has been billed to the customer, and SAP requires a cost element to account for this difference.
Cause: Revenue Recognition: The system has recognized revenue for a project or order that is greater than the amount billed to the customer. This can happen due to various reasons, such as: Incorrect revenue recognition settings. Timing differences between revenue recognition and billing. Manual entries or adjustments that have not been properly accounted for. Missing Cost Element: The system requires a cost element to record the excess revenue, but it has not been defined in the system.
Solution: To resolve the KJ314 error,
Get instant SAP help. Sign up for our Free Essentials Plan.
KJ313
Create a cost element for valuated actual cost of complaints/commissions
What causes this issue? The actual costs of complaints and commissions (costs of category P) are valuated and updated so that the system can tell whe...
KJ312
Create a cost element for valuated actual costs
What causes this issue? Actual costs are valuated and updated so that the system can tell whether postings have already been made to an object for wh...
KJ315
Create a cost element for revenue surplus
What causes this issue? If you are using the POC method to perform revenue-based results analysis, the system calculates a revenue surplus if the act...
KJ316
Create a cost element for POC profit increase
What causes this issue? If you are using the <DS:GLOS.POC_method>POC method</> to perform revenue-based <DS:GLOS.results_analysis>r...
Click on this link to search all SAP messages.