Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 113
Message text: Include activity only with cost element category &3
You want to input activities from sender cost center/activity type
&V1&/&V2& under cost element for order settlement &V4&.
Since you have set the Actual activity type category to Target=actual
activity allocation (category 5) for the used version and fiscal year,
this activity can only be input under allocation cost element &V3& of
the sender.
The entry is not accepted
For activity input use allocation cost element &V3&.
Error message extract from SAP system. Copyright SAP SE.
K8113
- Include activity only with cost element category &3 ?The SAP error message K8113 ("Include activity only with cost element category &3") typically occurs in the context of controlling (CO) when you are trying to include an activity type in a cost center or internal order that is not compatible with the specified cost element category.
Cause: The error is triggered when: You are attempting to assign an activity type to a cost center or internal order that does not have the appropriate cost element category. The cost element category defined for the activity type does not match the cost element category of the cost center or internal order you are trying to use.
Solution: To resolve this error, you can take the following steps: Check Cost Element Category: Go to the configuration settings for the cost element in question. You can do this in the SAP GUI by navigating to the relevant transaction (e.g., OKB2 for cost element categories). Ensure that the cost element category assigned to
Get instant SAP help. Sign up for our Free Essentials Plan.
K8112
You cannot include activity from target=actual activity allocation
What causes this issue? You want to input activities from sender cost center/activity type &V1&/&V2&. Since you have set the Actual a...
K8111
Secondary cost element & is not valid for resource planning
What causes this issue? You want to carry out a resource planning with cost element &V1&. However, in fiscal year &V2& this has only...
K8114
Process quantity from target=actual allocation cannot be included
What causes this issue? You want to input process quantities from sender business process &V1&. Since you have set the Actual activity type c...
K8115
Include process quantity only with cost element category &3
What causes this issue? You want to input process quantities from sender business process &V1& under order settlement cost element &V4&am...
Click on this link to search all SAP messages.