Do you have any question about this error?
Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 219
Message text: &1 &2: Start constraint conflicts with fixed finish
The fixed finish date of the project element is before its fixed start
date.
The system sets the duration of the project element to zero. The system
may calculate the dates incorrectly, for example,
if there are no actual start or finish dates.
Correct the fixed start date or the fixed finish date.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED219
- &1 &2: Start constraint conflicts with fixed finish ?The SAP error message DPR_SHARED219 indicates a conflict between a start constraint and a fixed finish date in a project management context, typically within SAP Project System (PS) or SAP Portfolio and Project Management (PPM). This error arises when the scheduling of a task or activity is not feasible due to conflicting constraints.
Cause:
- Start Constraint: A start constraint is a condition that specifies when a task must begin. For example, it may be set to start on a specific date or after the completion of a predecessor task.
- Fixed Finish Date: A fixed finish date is a constraint that specifies when a task must be completed. This means that the task cannot finish later than this date.
- Conflict: The error occurs when the defined start constraint does not allow the task to finish by the fixed finish date. For instance, if a task is set to start after a certain date but also has a fixed finish date that is earlier than the calculated finish date based on the start constraint, a conflict arises.
Solution:
To resolve the DPR_SHARED219 error, you can take the following steps:
- Review Constraints: Check the start and finish constraints of the task in question. Ensure that they are logically consistent and do not conflict with each other.
- Adjust Start Constraint: If the start constraint is too restrictive, consider adjusting it to allow for an earlier start date that aligns with the fixed finish date.
- Modify Fixed Finish Date: If the fixed finish date is not critical, you may consider changing it to accommodate the start constraint.
- Check Dependencies: Review any predecessor or successor relationships that may be influencing the scheduling of the task. Ensure that these relationships are set correctly.
- Recalculate Dates: After making adjustments, recalculate the project dates to ensure that all tasks are scheduled correctly without conflicts.
Related Information:
By carefully reviewing and adjusting the constraints, you should be able to resolve the DPR_SHARED219 error and ensure that your project scheduling is accurate and conflict-free.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED218
&1 &2: Actual start conflicts with fixed finish
What causes this issue? The fixed finish of the project element is before its actual start.System Response The system ignores the fixed finish and c...
DPR_SHARED217
&1 &2: Fixed or actual start conflicts with end of time frame
What causes this issue? The system calculated a finish from the fixed start or the actual start and the duration of the project element. The finish i...
DPR_SHARED220
&1 &2: Start date (&3) conflicts with finish date (&3)
What causes this issue? The finish date (&V3&) of the project element is before its start date ( &V3&).System Response The system ma...
DPR_SHARED221
&1 &2: Actual start conflicts with actual finish
What causes this issue? The actual finish of the project element is before its actual start.System Response The system may calculate the dates incor...
Click on this link to search all SAP messages.