Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 217
Message text: &1 &2: Fixed or actual start conflicts with end of time frame
The system calculated a finish from the fixed start or the actual start
and the duration of the project element. The finish is outside the time
frame specified by the superior project element.
The system ignores the time frame and sets the calculated finish.
Check whether the fixed start or the actual start of the project element
is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED217
- &1 &2: Fixed or actual start conflicts with end of time frame ?The SAP error message DPR_SHARED217 indicates that there is a conflict between the fixed or actual start date of a project or task and the end of the defined time frame. This typically occurs in project management scenarios within SAP, particularly in the context of project planning and scheduling.
Cause:
- Time Frame Mismatch: The actual or fixed start date of a task is set to a date that falls outside the defined time frame of the project or planning period.
- Incorrect Dates: The dates entered for the task or project may be incorrect or not aligned with the overall project schedule.
- Dependencies: There may be dependencies or constraints that are causing the start date to conflict with the end of the time frame.
- Project Structure Changes: Changes in the project structure or timeline that have not been updated in all related tasks can lead to this error.
Solution:
- Check Dates: Review the start and end dates of the project and the specific task that is causing the error. Ensure that the actual or fixed start date is within the defined time frame.
- Adjust Time Frame: If necessary, adjust the overall time frame of the project to accommodate the actual or fixed start date.
- Update Dependencies: Review any dependencies or constraints associated with the task and ensure they are correctly set up.
- Re-evaluate Task Scheduling: If the task is part of a larger project, consider re-evaluating the scheduling of tasks to ensure they align with the overall project timeline.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing project timelines and resolving scheduling conflicts.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a project management expert familiar with your specific SAP configuration.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED216
&1 &2: Fixed/actual start conflicts with the date of a successor
What causes this issue? During backward scheduling of the project element, the system calculated a start from a successor relationship and the durati...
DPR_SHARED215
&1 &2: Calculated dates are outside the specified time frame
What causes this issue? The calculated dates of the project element are outside the time frame defined by the superior project element. Example: You ...
DPR_SHARED218
&1 &2: Actual start conflicts with fixed finish
What causes this issue? The fixed finish of the project element is before its actual start.System Response The system ignores the fixed finish and c...
DPR_SHARED219
&1 &2: Start constraint conflicts with fixed finish
What causes this issue? The fixed finish date of the project element is before its fixed start date.System Response The system sets the duration of ...