Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 216
Message text: &1 &2: Fixed/actual start conflicts with the date of a successor
During backward scheduling of the project element, the system calculated
a start from a successor relationship and the duration of the project
element. The start is before the fixed start or before the actual start
of the project element.
The system ignores the successor relationship and uses the fixed start
or the actual start as the calculated start of the project element.
The system calculates the finish from this date using the duration of
the project element.
Check whether the fixed start or actual start is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED216
- &1 &2: Fixed/actual start conflicts with the date of a successor ?The SAP error message DPR_SHARED216 indicates that there is a conflict between the fixed or actual start date of a task and the date of its successor task in a project. This typically occurs in project management scenarios where tasks are interdependent, and the scheduling of one task affects the timing of another.
Cause:
Fixed/Actual Start Date Conflict: The task has a fixed or actual start date that does not align with the start date of its successor task. This can happen if:
- The predecessor task is scheduled to finish after the successor task is supposed to start.
- The fixed start date of the predecessor is set in such a way that it conflicts with the successor's planned start date.
Task Dependencies: The dependencies between tasks (like Finish-to-Start, Start-to-Start, etc.) are not properly configured, leading to scheduling conflicts.
Manual Adjustments: If manual adjustments were made to the schedule without considering the dependencies, it can lead to this error.
Solution:
Check Task Dependencies: Review the dependencies between the tasks. Ensure that the predecessor task is scheduled to finish before the successor task starts. Adjust the dependencies if necessary.
Adjust Dates: Modify the fixed or actual start date of the predecessor task to ensure it aligns with the successor task's start date. You may need to:
- Change the fixed start date to an earlier date.
- Adjust the successor task's start date to accommodate the predecessor's schedule.
Re-evaluate Scheduling: If the project schedule has been altered, re-evaluate the entire project timeline to ensure that all tasks are properly sequenced and that there are no conflicts.
Use Scheduling Tools: Utilize SAP's scheduling tools to automatically adjust dates based on dependencies. This can help prevent manual errors.
Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing task dependencies and scheduling in your version of SAP.
Related Information:
By addressing the underlying causes of the error and ensuring proper task management practices, you can resolve the DPR_SHARED216 error and maintain a smooth project schedule.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED215
&1 &2: Calculated dates are outside the specified time frame
What causes this issue? The calculated dates of the project element are outside the time frame defined by the superior project element. Example: You ...
DPR_SHARED214
&1 &2: Finish constraint conflicts with start of time frame
What causes this issue? The system calculated a start date using the fixed finish date and the duration of the project element. This fixed start date...
DPR_SHARED217
&1 &2: Fixed or actual start conflicts with end of time frame
What causes this issue? The system calculated a finish from the fixed start or the actual start and the duration of the project element. The finish i...
DPR_SHARED218
&1 &2: Actual start conflicts with fixed finish
What causes this issue? The fixed finish of the project element is before its actual start.System Response The system ignores the fixed finish and c...