Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 218
Message text: &1 &2: Actual start conflicts with fixed finish
The fixed finish of the project element is before its actual start.
The system ignores the fixed finish and calculates the finish from the
actual start and the duration.
Correct the fixed finish.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED218
- &1 &2: Actual start conflicts with fixed finish ?The SAP error message DPR_SHARED218 indicates that there is a conflict between the actual start date of a task and its fixed finish date in a project. This typically occurs in project management scenarios where tasks have defined constraints that dictate when they can start and finish.
Cause: Fixed Finish Date Constraint: The task has a fixed finish date set, which means it cannot finish later than this date. Actual Start Date: The actual start date of the task has been recorded or updated to a date that would cause the task to finish later than the fixed finish date. Dependencies: There may be dependencies or relationships with other tasks that are affecting the scheduling of the task in question.
Solution: Review Task Dates: Check the actual start date of the task and compare it with the fixed finish date. Ensure that the actual start date does not push the finish date beyond the fixed finish
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED217
&1 &2: Fixed or actual start conflicts with end of time frame
What causes this issue? The system calculated a finish from the fixed start or the actual start and the duration of the project element. The finish i...
DPR_SHARED216
&1 &2: Fixed/actual start conflicts with the date of a successor
What causes this issue? During backward scheduling of the project element, the system calculated a start from a successor relationship and the durati...
DPR_SHARED219
&1 &2: Start constraint conflicts with fixed finish
What causes this issue? The fixed finish date of the project element is before its fixed start date.System Response The system sets the duration of ...
DPR_SHARED220
&1 &2: Start date (&3) conflicts with finish date (&3)
What causes this issue? The finish date (&V3&) of the project element is before its start date ( &V3&).System Response The system ma...
Click on this link to search all SAP messages.