Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 220
Message text: &1 &2: Start date (&3) conflicts with finish date (&3)
The finish date (&V3&) of the project element is before its start date (
&V3&).
The system may calculate the dates incorrectly if you are using
constraint dates.
Correct the start date (&V3&) or finish date (&V3&).
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED220
- &1 &2: Start date (&3) conflicts with finish date (&3) ?The SAP error message DPR_SHARED220 indicates a conflict between the start date and finish date of a project or task in the SAP Project System (PS) or Project Management (PM) module. Specifically, the error message states that the start date conflicts with the finish date, meaning that the start date is set to a time that is later than the finish date, which is logically incorrect.
Cause: Incorrect Date Entry: The most common cause is that the user has entered the start date and finish date incorrectly, leading to a situation where the start date is after the finish date. Data Migration Issues: If data has been migrated from another system, there may be inconsistencies in the date formats or values. System Configuration: There may be configuration settings in the project management module that enforce certain date constraints, leading to this error if not adhered to.
Solution: Check Dates: Review the start and finish dates for
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED219
&1 &2: Start constraint conflicts with fixed finish
What causes this issue? The fixed finish date of the project element is before its fixed start date.System Response The system sets the duration of ...
DPR_SHARED218
&1 &2: Actual start conflicts with fixed finish
What causes this issue? The fixed finish of the project element is before its actual start.System Response The system ignores the fixed finish and c...
DPR_SHARED221
&1 &2: Actual start conflicts with actual finish
What causes this issue? The actual finish of the project element is before its actual start.System Response The system may calculate the dates incor...
DPR_SHARED222
Constraint date is missing for the start constraint
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...