Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 214
Message text: &1 &2: Finish constraint conflicts with start of time frame
The system calculated a start date using the fixed finish date and the
duration of the project element. This fixed start date is before the
beginning of the time frame specified by the superior project element.
The system ignores the time frame and sets the calculated start.
Check whether the fixed finish date is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED214
- &1 &2: Finish constraint conflicts with start of time frame ?The SAP error message DPR_SHARED214 indicates that there is a conflict between a finish constraint and the start of a time frame in a project. This typically occurs in the context of project management within SAP, particularly when dealing with project planning and scheduling.
Cause:
The error arises when:
To resolve this error, you can take the following steps:
Check Task Constraints:
Adjust Time Frame:
Modify Constraints:
Review Dependencies:
Consult Documentation:
Test Changes:
By following these steps, you should be able to resolve the DPR_SHARED214 error and ensure that your project scheduling is accurate and conflict-free.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED213
&1 &2: Start constraint conflicts with end of time frame
What causes this issue? The system calculated a finish date using the fixed start date and the duration of the project element. This finish date is a...
DPR_SHARED212
&1 &2: Finish constraint conflicts with determined finish
What causes this issue? A constraint is set for the finish of the project element. In backward scheduling, the system calculates the finish (latest f...
DPR_SHARED215
&1 &2: Calculated dates are outside the specified time frame
What causes this issue? The calculated dates of the project element are outside the time frame defined by the superior project element. Example: You ...
DPR_SHARED216
&1 &2: Fixed/actual start conflicts with the date of a successor
What causes this issue? During backward scheduling of the project element, the system calculated a start from a successor relationship and the durati...
Click on this link to search all SAP messages.