How To Fix DPR_SHARED212 - &1 &2: Finish constraint conflicts with determined finish


DPR_SHARED212 - Overview

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 212

  • Message text: &1 &2: Finish constraint conflicts with determined finish

  • Show details Hide details
  • What causes this issue?

    A constraint is set for the finish of the project element. In backward
    scheduling, the system calculates the finish (latest finish) of the
    project element step by step:
    Actual finish of the project element (you can use the BAdI to ignore
    this).
    If no actual finish has been set, the system determines it from the
    successor relationships of the project element.
    If no actual finish was found in the previous steps, the system takes
    the finish of the higher-level project element.
    The system then compares the determined finish (latest finish) with the
    constraint for the finish. The warning appears if the finish conflicts
    with the constraint for the finish.

    System Response

    The system sets the finish of the constraint as the calculated finish.

    How to fix this error?

    Check whether the constraint for the finish is realistic.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message DPR_SHARED212 - &1 &2: Finish constraint conflicts with determined finish ?
    The SAP error message DPR_SHARED212 indicates that there is a conflict between a finish constraint and the determined finish date of a project or task in the Project Management module. This typically occurs when the scheduling of a task is not aligned with its constraints, such as a finish date that is either too early or too late compared to what is defined in the system.
    
    Cause: Finish Constraint: The task has a finish constraint (e.g., "Must Finish On", "Finish No Later Than") that conflicts with the calculated finish date based on the task's dependencies and durations. Dependencies: There may be dependencies on other tasks that affect the scheduling of the task in question. Resource Availability: Resource constraints or unavailability may lead to a situation where the task cannot be completed by the determined finish date. Incorrect Dates: Manual entry of dates that do not align with the project schedule can also lead to this

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author