Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 213
Message text: &1 &2: Start constraint conflicts with end of time frame
The system calculated a finish date using the fixed start date and the
duration of the project element. This finish date is after the end of
the time frame specified by the superior project element.
The system ignores the time frame and sets the calculated finish.
Check whether the fixed start date of the project element is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED213
- &1 &2: Start constraint conflicts with end of time frame ?The SAP error message DPR_SHARED213 indicates that there is a conflict between the start constraint and the end of the time frame for a project or task in the SAP Project Management module. This typically occurs when the scheduling constraints set for a task do not align with the defined time frame for the project or the task itself.
Cause: Start and End Dates Conflict: The start date of a task is set to begin after the end date of the project or the task's time frame. Constraints Misconfiguration: There may be constraints applied to the task that are not compatible with the overall project timeline. Dependencies: The task may have dependencies that are not properly aligned with the project schedule, causing a conflict in the timing. Resource Availability: If resources are not available during the defined time frame, it can lead to scheduling conflicts.
Solution: Check Task Dates: Review the start and end dates of the
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED212
&1 &2: Finish constraint conflicts with determined finish
What causes this issue? A constraint is set for the finish of the project element. In backward scheduling, the system calculates the finish (latest f...
DPR_SHARED211
&1 &2: Start constraint conflicts with determined start
What causes this issue? A constraint is set for the start of the project element. In forward scheduling, the system calculates the start (earliest st...
DPR_SHARED214
&1 &2: Finish constraint conflicts with start of time frame
What causes this issue? The system calculated a start date using the fixed finish date and the duration of the project element. This fixed start date...
DPR_SHARED215
&1 &2: Calculated dates are outside the specified time frame
What causes this issue? The calculated dates of the project element are outside the time frame defined by the superior project element. Example: You ...