Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 445
Message text: Planned order &: Rescheduling with production version was rejected
If you have set the indicator <ls>Term.resched.with prod.version</> in
the strategy profile then the rescheduling of operations in planned
orders to another work center is terminated if the work center is not
specified as the production line in a production version of the
material.
The operation in the planned order is not rescheduled.
Deactivate the indicator <ls>Term.resched.with prod.version</> in the
strategy profile.
Deactivate the indicator <ls>Reschedule with production version</> in
the strategy profile.
Error message extract from SAP system. Copyright SAP SE.
CY445
- Planned order &: Rescheduling with production version was rejected ?The SAP error message CY445, which states "Planned order &: Rescheduling with production version was rejected," typically occurs in the context of production planning and scheduling within the SAP system. This error indicates that there was an issue with rescheduling a planned order that is linked to a production version. Causes: Production Version Issues: The production version associated with the planned order may not be valid or may not exist. Material Master Data: The material master data may not be correctly set up, particularly the production version or the relevant parameters. Capacity Constraints: There may be capacity constraints in the production resources that prevent the rescheduling of the planned order. Order Status: The status of the planned order may not allow for rescheduling (e.g., if it is already released or in process). Date Constraints: The dates associated with the planned order may not align with the production version's validity period. Solutions: Check Production Version: Verify that the production
Get instant SAP help. Sign up for our Free Essentials Plan.
CY444
Planned order & could not be rescheduled for the next line
What causes this issue? Planned orders are scheduled with new production versions in the following cases when dispatching or rescheduling: <ls>...
CY443
Planned order & was rescheduled using the next production version
What causes this issue? The system could not dispatch the planned order to the production line originally intended for it. A possible cause is, for e...
CY446
Change production version on error was not executed
What causes this issue? In the strategy profile, the planning functions <ZH> <ZK>setup time optimization</></> and <ZH>...
CY450
Planned order &1 operation &2 were deleted on rescheduling
What causes this issue? If you dispatch, reschedule or deallocate a planned order the system reschedules it. It reads in the new routing to do this. ...
Click on this link to search all SAP messages.