Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 443
Message text: Planned order & was rescheduled using the next production version
The system could not dispatch the planned order to the production line
originally intended for it. A possible cause is, for example, a
capacity overload on this line.
Since you have activated the indicator <ls>Error handling when changing
production version</> the planned order was scheduled for the
production line entered for the production version that is next
alphanumerically.
However, the operation has not yet been dispatched.
Dispatch all the rescheduled operations in the planned orders to the
new production lines.
Error message extract from SAP system. Copyright SAP SE.
CY443
- Planned order & was rescheduled using the next production version ?The SAP error message CY443 indicates that a planned order has been rescheduled using the next production version. This typically occurs in the context of production planning and scheduling within SAP's Material Requirements Planning (MRP) module. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- Production Version Change: The planned order is linked to a specific production version, and the system has determined that a different production version is more suitable for the rescheduling process.
- Material Availability: The system may have identified that the materials required for the original production version are not available, prompting a switch to the next available version.
- Configuration Settings: The settings in the material master or production planning configuration may dictate that planned orders can be rescheduled to the next production version based on certain criteria (like lead times, availability, etc.).
Solution:
- Review Production Versions: Check the production versions defined for the material in the material master (transaction code MM03). Ensure that the production versions are correctly set up and that the necessary components are available for the selected version.
- Check Material Availability: Use transaction code MD04 (Stock/Requirements List) to check the availability of materials and components for the planned order. If materials are missing, consider adjusting the procurement or production plans.
- Adjust Planning Parameters: Review the planning parameters in the MRP settings (transaction code OMD0) to ensure they align with your production strategy. This includes lead times, lot sizes, and other relevant settings.
- Manual Rescheduling: If the automatic rescheduling is not desired, you can manually adjust the planned order to the original production version if the conditions allow it.
- Consult Documentation: Refer to SAP documentation or help files for specific details on the error message and its implications in your version of SAP.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a consultant who specializes in SAP production planning.
Get instant SAP help. Start your 7-day free trial now.
CY442
No planned orders with valid production versions exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CY441
Invalid production version for planned order &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CY444
Planned order & could not be rescheduled for the next line
What causes this issue? Planned orders are scheduled with new production versions in the following cases when dispatching or rescheduling: <ls>...
CY445
Planned order &: Rescheduling with production version was rejected
What causes this issue? If you have set the indicator <ls>Term.resched.with prod.version</> in the strategy profile then the rescheduling...
Click on this link to search all SAP messages.