Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 446
Message text: Change production version on error was not executed
In the strategy profile, the planning functions <ZH>
<ZK>setup time optimization</></> and <ZH><ZK>change production version
on error</></> are active. However, you cannot change the production
version after performing setup time optimization.
The system does not change the production version for the affected
planned order.
Do not use <ZH><ZK>setup time optimization</></> and <ZH><ZK>change
production version on error</></> at the same time.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
CY446
- Change production version on error was not executed ?The SAP error message CY446 ("Change production version on error was not executed") typically occurs in the context of production planning and control, particularly when dealing with production versions in SAP's Material Management (MM) or Production Planning (PP) modules. This error indicates that there was an issue with changing the production version of a material, often due to inconsistencies or errors in the data. Causes: Data Inconsistencies: There may be inconsistencies in the master data related to the material, such as the Bill of Materials (BOM) or routing. Locked Records: The production version or related records might be locked by another user or process, preventing changes. Missing Data: Required fields or data might be missing in the production version or related master data. Authorization Issues: The user may not have the necessary authorizations to change the production version.
Configuration Issues: There may be configuration settings in the system that prevent the change from being executed. Solutions: Check Data
Get instant SAP help. Sign up for our Free Essentials Plan.
CY445
Planned order &: Rescheduling with production version was rejected
What causes this issue? If you have set the indicator <ls>Term.resched.with prod.version</> in the strategy profile then the rescheduling...
CY444
Planned order & could not be rescheduled for the next line
What causes this issue? Planned orders are scheduled with new production versions in the following cases when dispatching or rescheduling: <ls>...
CY450
Planned order &1 operation &2 were deleted on rescheduling
What causes this issue? If you dispatch, reschedule or deallocate a planned order the system reschedules it. It reads in the new routing to do this. ...
CY451
Changes cannot be made to planned orders for planned independent reqmts
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.