Message type: E = Error
Message class: C2 - Other messages production orders
Message number: 310
Message text: WBS element & not (partially) released / technically completed
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
The SAP error message C2310 indicates that a Work Breakdown Structure (WBS) element is not fully released or technically completed. This error typically arises in project management scenarios when trying to perform certain actions (like posting costs, creating purchase orders, etc.) on a WBS element that is not in the correct status.
Cause:
- WBS Element Status: The WBS element may not be fully released. In SAP, WBS elements have different statuses (e.g., "Not Released," "Released," "Technically Completed"). If the WBS element is in a status that does not allow certain transactions, this error will occur.
- Project Definition Status: The overall project definition may also be in a status that restricts actions on its WBS elements.
- Authorization Issues: The user may not have the necessary authorizations to perform actions on the WBS element.
- Incomplete Planning: If the WBS element has not been fully planned or if there are missing components (like budget or resources), it may lead to this error.
Solution:
Check WBS Status:
- Go to the WBS element in the SAP system and check its status. You can do this using transaction code
CJ20N
(Project Builder) orCJ03
(Display WBS Element).- If the WBS element is not released, you can release it using transaction code
CJ02
(Change WBS Element) and selecting the "Release" option.Check Project Definition:
- Ensure that the project definition is also released. If the project definition is not released, you will need to release it first.
Review Authorizations:
- Ensure that the user has the necessary authorizations to perform actions on the WBS element. This may involve checking roles and permissions in the SAP system.
Complete Planning:
- Ensure that all necessary planning components (like budgets, resources, etc.) are in place for the WBS element. If any components are missing, complete the planning before attempting the action again.
Technical Completion:
- If the WBS element is technically completed, you may need to check if any further actions are required to finalize it. If you need to perform actions on a technically completed WBS, you may need to reverse the technical completion status.
Related Information:
CJ20N
: Project BuilderCJ02
: Change WBS ElementCJ03
: Display WBS ElementCJ01
: Create WBS ElementBy following these steps, you should be able to resolve the C2310 error and proceed with your project management tasks in SAP.
Get instant SAP help. Start your 7-day free trial now.
Feature | Free Access | Free Trial |
---|---|---|
Basic SAP error explanation | ![]() |
![]() |
Step-by-Step Usage Guide | ![]() |
![]() |
Interactive SAP Coach Assistance | ![]() |
![]() |
AI Troubleshooting for T-Code Errors | ![]() |
![]() |
C2309 First execute planning run (multi-level) for material &1
What causes this issue? The planned order cannot be converted as the related or...
C2308 Planned order &1 does not contain any reservations for phantom assemblies
What causes this issue? The system attempted to convert planning order &V1&...
C2311 Component & item & cannot be deleted (see long text)
What causes this issue? The selected component (material &V1&, item &am...
C2312 No more free item numbers (Please check)
What causes this issue? No further item numbers can be automatically assigned f...
SAP messages fall into 3 different categories: Error messages
(message type = E), Warnings (W) or Informational (I) messages.
An error message will prevent you from continuing your work - it is a hard stop and you need to fix the error before you can proceed. A warning message will stop your work, however, you can then bypass the warning by pressing the Enter key on your keyboard. That said, it is still good practice to investigate the cause of the warning message and address it. An information message will not stop your work and is truly just for informational purposes.
Click on this link to search all SAP messages.