Message type: E = Error
Message class: V4 - Nachrichten Verkauf (Variable Meldungen und EDI-Meldungen)
Message number: 004
Message text: The production go-ahead start time lies after the prod.go-ahead end time
You have entered a start date for cumulative production which is later
than the end date for cumulative production.
The system does not accept the entry or gives a warning message.
Please correct the entry in both data fields in cumulative production.
If both fields have not been correctly maintained, the cumulative
production go-ahead quantity, which is only for information purposes,
will not be able to be correctly determined.
Error message extract from SAP system. Copyright SAP SE.
V4004
- The production go-ahead start time lies after the prod.go-ahead end time ?The SAP error message V4004 indicates that there is a discrepancy in the scheduling of production orders, specifically that the production go-ahead start time is set to occur after the production go-ahead end time. This situation typically arises in the context of production planning and scheduling within the SAP system.
Cause:
- Incorrect Time Settings: The start and end times for the production go-ahead may have been entered incorrectly, leading to a situation where the start time is later than the end time.
- Scheduling Conflicts: There may be conflicts in the scheduling of production orders, such as overlapping orders or incorrect lead times.
- Master Data Issues: Problems with the master data for materials, production resources, or routing can lead to incorrect time calculations.
- Configuration Errors: Incorrect configuration in the production planning settings can also lead to this error.
Solution:
- Check Time Entries: Review the production order and ensure that the go-ahead start time is set before the go-ahead end time. Adjust the times accordingly.
- Review Scheduling Parameters: Check the scheduling parameters for the production order to ensure they are set correctly. This includes lead times, setup times, and processing times.
- Examine Master Data: Verify the master data for the materials and resources involved in the production order. Ensure that all relevant data is accurate and up-to-date.
- Adjust Production Order: If necessary, adjust the production order to resolve any conflicts or scheduling issues. This may involve rescheduling or reassigning resources.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on handling scheduling errors and understanding the implications of the error message.
Related Information:
By following these steps, you should be able to identify the cause of the V4004 error and implement the necessary corrections to resolve it.
Get instant SAP help. Sign up for our Free Essentials Plan.
V4003
The delivery date entered does not correspond to the document date
What causes this issue? You have entered a delivery date belonging to the last delivery note posted for this customer. It does not agree, however, wi...
V4002
The delivery entered does not exist in the document flow
What causes this issue? You have entered the delivery note number for the last delivery note posted for this customer. Because it could not be found ...
V4005
The material go-ahead start time lies after the mat.go-ahead end time
What causes this issue? You have entered a material go-ahead start date that is later than the material go-ahead end date.System Response The system...
V4006
The production go-ahead period is longer than the mat.go-ahead period
What causes this issue? You have entered a period for production go-ahead that is larger than the period for material go-ahead.System Response The s...