Message type: E = Error
Message class: SPROJECT - General Project Management Messages
Message number: 350
Message text: Planned start & is earlier than project start date &
You have specified a planned start which is before the project start
date &V2&. The planned start must be greater than or equal to the
project start date &V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Specify a planned start after &V2&.
Otherwise change the project start date in the project structure root
node activity data.
Error message extract from SAP system. Copyright SAP SE.
SPROJECT350
- Planned start & is earlier than project start date & ?The SAP error message SPROJECT350 indicates that there is a discrepancy between the planned start date of a project and the project's defined start date. Specifically, it means that the planned start date you are trying to set is earlier than the project's official start date, which is not allowed in the system.
Cause:
- Date Configuration: The planned start date you are entering is set before the project's start date defined in the project definition.
- Project Definition: The project might have been defined with a specific start date that is later than the planned start date you are trying to enter.
- Data Entry Error: There may have been a mistake in entering the dates, leading to this conflict.
Solution:
- Check Project Dates: Review the project definition to confirm the official start date. You can do this by navigating to the project in the SAP system and checking the project details.
- Adjust Planned Start Date: If the planned start date is indeed earlier than the project start date, you will need to adjust the planned start date to be on or after the project start date.
- Modify Project Definition: If necessary, and if it aligns with your project management strategy, you can consider changing the project start date to an earlier date, but this should be done with caution and proper authorization.
- Consult Documentation: Refer to your organization's project management guidelines or SAP documentation for any specific rules regarding project date management.
Related Information:
CJ20N
(Project Builder) or CJ02
(Change Project) to view and modify project details.If the issue persists after checking and adjusting the dates, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in project systems.
Get instant SAP help. Sign up for our Free Essentials Plan.
SPROJECT349
You are not authorized to change the system landscape
What causes this issue? You are not authorized for the action. You need the value <ZH>SYST</> for the field <ZH>PROJ_FUNC</> ...
SPROJECT348
You are not authorized to change the scenario selection
What causes this issue? You are not authorized for the action. You need the value <ZH>SCEN</> for the field <ZH>PROJ_FUNC</> ...
SPROJECT351
Planned end date & is later than project end date &
What causes this issue? You have specified a plan end which is after the project end date &V2&, but the plan end must be before or on the pro...
SPROJECT352
Planned start & is after project end date &
What causes this issue? You have specified a plan start after the project end date &V2&. It must be before the project end.System Response T...
Click on this link to search all SAP messages.