Message type: E = Error
Message class: SPROJECT - General Project Management Messages
Message number: 351
Message text: Planned end date & is later than project end date &
You have specified a plan end which is after the project end date &V2&,
but the plan end must be before or on the project end date &V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Specify a plan end before &V2&.
Otherwise change the project end date in the project structure root
node activity data.
Error message extract from SAP system. Copyright SAP SE.
SPROJECT351
- Planned end date & is later than project end date & ?Get instant SAP help. Start your 7-day free trial now.
SPROJECT350
Planned start & is earlier than project start date &
What causes this issue? You have specified a planned start which is before the project start date &V2&. The planned start must be greater tha...
SPROJECT349
You are not authorized to change the system landscape
What causes this issue? You are not authorized for the action. You need the value <ZH>SYST</> for the field <ZH>PROJ_FUNC</> ...
SPROJECT352
Planned start & is after project end date &
What causes this issue? You have specified a plan start after the project end date &V2&. It must be before the project end.System Response T...
SPROJECT353
Planned end date & is before project start date &
What causes this issue? You have specified a plan end before the project start date &V2&, but it must be later.System Response The system is...