Message type: E = Error
Message class: /SAPAPO/PP_OPTIMIZER -
Message number: 046
Message text: Resource &1: No available capacity in time frame &2 to &3
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/PP_OPTIMIZER046
- Resource &1: No available capacity in time frame &2 to &3 ?The SAP error message
/SAPAPO/PP_OPTIMIZER046
indicates that there is no available capacity for a specific resource during a given time frame. This error typically occurs in the context of production planning and optimization within the SAP Advanced Planning and Optimization (APO) module.Cause:
- Resource Capacity Limitations: The resource specified in the error message has reached its maximum capacity for the specified time frame. This could be due to scheduled maintenance, existing production orders, or other constraints.
- Incorrect Capacity Planning: The capacity planning settings for the resource may not be configured correctly, leading to an underestimation of available capacity.
- Time Frame Issues: The time frame specified in the error message may not align with the actual availability of the resource, possibly due to incorrect planning or scheduling.
- Resource Allocation Conflicts: Other production orders or processes may be using the same resource, leading to conflicts in capacity allocation.
Solution:
- Check Resource Availability: Review the capacity planning for the resource in question. Ensure that the resource is not overbooked and that there is sufficient capacity available for the planned production.
- Adjust Production Orders: If possible, reschedule or adjust existing production orders that are using the resource to free up capacity during the specified time frame.
- Modify Capacity Settings: If the resource's capacity settings are incorrect, adjust them in the SAP system to reflect the actual available capacity.
- Review Maintenance Schedules: Ensure that any planned maintenance or downtime for the resource is accurately reflected in the system and does not conflict with production needs.
- Use Alternative Resources: If the primary resource is unavailable, consider using alternative resources that can fulfill the production requirements.
- Consult with Production Planners: Collaborate with production planners to understand the constraints and find a feasible solution to the capacity issue.
Related Information:
/SAPAPO/OPTIMIZER
to analyze the optimizer settings or /SAPAPO/RESOURC
to check resource details.By following these steps and understanding the underlying causes, you should be able to resolve the error and ensure that your production planning processes run smoothly.
Get instant SAP help. Sign up for our Free Essentials Plan.
/SAPAPO/PP_OPTIMIZER045
Resource &1: increase capacity overload is not taken into account
What causes this issue? The increase capacity of resource &V1& is being loaded with more than its available capacity between bucket &V2&a...
/SAPAPO/PP_OPTIMIZER044
Resource &1: Not available or has no available capacity
What causes this issue? Resource &V1& is not available from &V2& until &V3& or has no available capacity.How to fix this erro...
/SAPAPO/PP_OPTIMIZER049
Transportation resource &1: The capacity is not valid
What causes this issue? Transportation resource &V1&: The transportation capacity for each vehicle is &V2&. This value must be greate...
/SAPAPO/PP_OPTIMIZER051
Transportation lane &1: Shipment duration rounded to 0
What causes this issue? The duration of a shipment using transportation lane &V1& has been rounded to 0 days.System Response The transportat...
Click on this link to search all SAP messages.