Message type: E = Error
Message class: REMPT - Message Class for REM Planning Table (Rel. 99)
Message number: 314
Message text: No capacity requirements were determined (see Customizing)
No capacity requirements were created for the planned order.
This may be as a result of the following:
It is set in Customizing that no capacity requirements are to be
created for the scheduling level you used to access the planning table.
You define the scheduling levels for the various types of planned
orders in Customizing:
<DS:TRAN.OPU5>Proceed with function</>
The routings in the production version in the material master record
(MRP 4 screen) must be entered according to the scheduling level
settings in Customizing (Determining scheduling and capacity reqmts via
detailed or rate-based planning).
<DS:TRAN.MM02>Proceed with function</>
If you have made any changes, you have to restart the planning table to
activate these changes.
Error message extract from SAP system. Copyright SAP SE.
REMPT314
- No capacity requirements were determined (see Customizing) ?The SAP error message REMPT314 "No capacity requirements were determined (see Customizing)" typically occurs in the context of production planning and capacity management. This message indicates that the system was unable to determine any capacity requirements for a particular production order or planning scenario. Here are the potential causes, solutions, and related information for this error:
Causes:
- Missing Master Data: The relevant master data (like work centers, routing, or production versions) may not be properly maintained or may be missing.
- Incorrect Configuration: The configuration settings in the Customizing (SPRO) may not be set up correctly for capacity planning.
- Routing Issues: The routing for the production order may not be defined correctly, or it may not be assigned to the material.
- Work Center Issues: The work center may not have the necessary capacity defined, or it may not be assigned to the correct production resources.
- Planning Parameters: The planning parameters for the material or production order may not be set correctly, leading to no capacity being calculated.
- Production Version: If a production version is not assigned to the material, the system may not be able to determine capacity requirements.
Solutions:
Check Master Data:
- Ensure that the work centers, routings, and production versions are correctly defined and assigned to the material.
- Verify that the work center has the necessary capacity defined.
Review Customizing Settings:
- Go to SPRO and check the settings under "Production" and "Capacity Planning" to ensure that all necessary configurations are in place.
- Ensure that the capacity planning settings are activated for the relevant planning areas.
Validate Routing:
- Check the routing assigned to the production order to ensure it is valid and correctly linked to the work center.
- Make sure that the routing contains the necessary operations and that they are correctly defined.
Check Production Version:
- Ensure that a valid production version is assigned to the material in the material master.
- If necessary, create or adjust the production version to include the correct routing and work center.
Analyze Planning Parameters:
- Review the planning parameters for the material in the material master to ensure they are set correctly for capacity planning.
Test with Different Scenarios:
- If possible, test the production order with different materials or scenarios to see if the issue persists, which can help isolate the problem.
Related Information:
CO01
(Create Production Order), CO02
(Change Production Order), CR01
(Create Work Center), and CA01
(Create Routing) to check and maintain the relevant data.By following these steps, you should be able to identify the root cause of the REMPT314 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
REMPT313
Scheduling levels not maintained in Customizing
What causes this issue? Problems occurred when scheduling the planned order. This may be as a result of the following: You have not maintained Custom...
REMPT312
Scheduling not executed for plnd orders of material &1, version &2
What causes this issue? The planned order was not scheduled. This may be due to one of the following reasons, for example: The scheduling level (deta...
REMPT315
No prod. dates for material &1, version &2, production line &3
What causes this issue? The planned order has no production dates for the combination of material, production version and production line you specifi...
REMPT316
Detailed or rate-based sched. and sequencing active simultaneously
What causes this issue? Detailed or rate-based scheduling and sequecing are all active at the same time.How to fix this error? You must choosing one...