How To Fix REMPT316 - Detailed or rate-based sched. and sequencing active simultaneously


REMPT316 - Overview

  • Message type: E = Error

  • Message class: REMPT - Message Class for REM Planning Table (Rel. 99)

  • Message number: 316

  • Message text: Detailed or rate-based sched. and sequencing active simultaneously

  • Show details Hide details
  • What causes this issue?

    Detailed or rate-based scheduling and sequecing are all active at the
    same time.

    How to fix this error?

    You must choosing one scheduling type:
    Capacity scheduling (detailed or rate-based planning).
    Or, line-based scheduling (sequencing).
    You define the scheduling levels for the various types of planned
    orders in Customizing:
    <DS:TRAN.OPU5>Proceed with functionn</>
    The routings in the production version in the material master record
    (MRP 4 screen) must be entered according to the scheduling level
    settings in Customizing (Determining scheduling and capacity reqmts via
    detailed or rate-based planning).
    <DS:TRAN.MM02>Proceed with function</>
    If you have made any changes, you have to restart the planning table to
    activate these changes.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message REMPT316 - Detailed or rate-based sched. and sequencing active simultaneously ?
    The SAP error message REMPT316 indicates that both detailed scheduling and rate-based scheduling are active at the same time for a production process. This situation is not allowed in SAP, as these two scheduling methods are mutually exclusive.
    
    Cause: The error occurs when: You have configured a production process (like a production order or a planned order) to use both detailed scheduling and rate-based scheduling. This can happen due to incorrect settings in the production planning configuration or in the specific order settings.
    Solution: To resolve this error, you need to ensure that only one scheduling method is active for the relevant production process. Here are the steps you can take: Check Order Settings: Go to the production order or planned order in question. Check the scheduling parameters to see if both detailed scheduling and rate-based scheduling are enabled. Adjust Scheduling Parameters: If detailed scheduling is not required, disable it in the order settings. If rate-based scheduling is needed, ensure that detailed

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker