Do you have any question about this error?
Message type: E = Error
Message class: REMPT - Message Class for REM Planning Table (Rel. 99)
Message number: 315
Message text: No prod. dates for material &1, version &2, production line &3
The planned order has no production dates for the combination of
material, production version and production line you specified.
This may be as a result of the following, for example:
The planned order was scheduled but not using the production line you
selected. (The production line is determined by the production version
you entered in a planned order.)
One possibility of finding out what is causing the problem is:
To access the planned order from the detailed dialog box in the table
via "Change" and reschedule the planned order. Check the scheduling log
by choosing "Goto --> Scheduling log". More information is displayed in
the log's warning or error messages.
Error message extract from SAP system. Copyright SAP SE.
REMPT315
- No prod. dates for material &1, version &2, production line &3 ?The SAP error message REMPT315 indicates that there are no production dates available for a specific material, version, and production line combination. This error typically occurs in the context of production planning and execution within the SAP system, particularly in the SAP Advanced Planning and Optimization (APO) module or in the Production Planning (PP) module.
Cause:
Missing Production Dates: The primary cause of this error is that the system cannot find any valid production dates for the specified material, version, and production line. This could be due to:
- No production orders being created for the material.
- The production line not being scheduled for the specified time period.
- The material not being set up correctly in the system.
- The version of the material not having any planned production dates.
Configuration Issues: There may be configuration issues in the production planning settings that prevent the system from generating or displaying production dates.
Master Data Issues: The material master data or production version may not be correctly maintained, leading to the absence of production dates.
Solution:
Check Production Orders: Verify if there are any production orders created for the material in question. If not, create the necessary production orders.
Review Production Planning Settings: Ensure that the production line is correctly scheduled and that the planning settings are appropriate for the material and version.
Check Material Master Data:
- Go to the material master (transaction code MM03) and check the relevant views (e.g., Basic Data, MRP, Work Scheduling) to ensure that all necessary data is maintained.
- Ensure that the production version is correctly assigned to the material.
Check Version Control: If version control is being used, ensure that the correct version is active and has valid production dates.
Run MRP: If applicable, run the Material Requirements Planning (MRP) process to generate production proposals and dates for the material.
Consult Documentation: Review any relevant SAP documentation or notes related to this error message for additional troubleshooting steps.
Related Information:
Transaction Codes: Familiarize yourself with relevant transaction codes such as:
SAP Notes: Check SAP Notes for any known issues or patches related to this error message.
User Roles and Authorizations: Ensure that the user has the necessary authorizations to view and manage production data.
Consult with SAP Support: If the issue persists after checking the above points, consider reaching out to SAP support for further assistance.
By following these steps, you should be able to identify the root cause of the REMPT315 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
REMPT314
No capacity requirements were determined (see Customizing)
What causes this issue? No capacity requirements were created for the planned order. This may be as a result of the following: It is set in Customizi...
REMPT313
Scheduling levels not maintained in Customizing
What causes this issue? Problems occurred when scheduling the planned order. This may be as a result of the following: You have not maintained Custom...
REMPT316
Detailed or rate-based sched. and sequencing active simultaneously
What causes this issue? Detailed or rate-based scheduling and sequecing are all active at the same time.How to fix this error? You must choosing one...
REMPT320
Capacity category of work center &1 was set to &2
What causes this issue? The basis the system uses for scheduling and to calculate capacity requirements is not the same. A possible explanation is th...