How To Fix REMPT312 - Scheduling not executed for plnd orders of material &1, version &2


REMPT312 - Overview

  • Message type: E = Error

  • Message class: REMPT - Message Class for REM Planning Table (Rel. 99)

  • Message number: 312

  • Message text: Scheduling not executed for plnd orders of material &1, version &2

  • Show details Hide details
  • What causes this issue?

    The planned order was not scheduled.
    This may be due to one of the following reasons, for example:
    The scheduling level (detailed or rate-based planning) you used to
    access the planning table and the one used for scheduling are not the
    same.
    No suitable routing could be found.

    How to fix this error?

    One possibility of finding out what is causing the problem is:
    To access the planned order from the detailed dialog box in the table
    via "Change" and reschedule the planned order. Check the scheduling log
    by choosing "Goto --> Scheduling log". More information is displayed in
    the log's warning or error messages.
    You define the scheduling levels for the various types of planned
    orders in Customizing.
    <DS:TRAN.OPU5>Proceed with function</>
    You must enter the routings in the production version in the material
    master record (MRP 4 screen) according to the scheduling level settings
    in Customizing (determine scheduling and capacity requirements via
    detailed or rate-based planning).
    <DS:TRAN.MM02>Proceed with function</>
    If you have made any changes, you have to restart the planning table to
    activate the changes.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message REMPT312 - Scheduling not executed for plnd orders of material &1, version &2 ?
    The SAP error message REMPT312 indicates that scheduling was not executed for planned orders of a specific material and version. This error typically arises in the context of production planning and scheduling within the SAP system.
    
    Cause: The error can be caused by several factors, including: Missing or Incorrect Master Data: The material master or the routing for the planned order may not be set up correctly. This includes missing production versions or incorrect settings in the material master. Scheduling Parameters: The scheduling parameters for the planned order may not be defined correctly, leading to the inability to execute scheduling. Order Status: The planned order may be in a status that does not allow scheduling (e.g., it may be locked or not released). Capacity Constraints: If there are capacity constraints in the production resources, scheduling may not be possible. Version Control: The version specified in the planned order may not be valid or may not exist in

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant