Do you have any question about this error?
Message type: E = Error
Message class: NAA - Subsequent settlement (Purchasing)
Message number: 638
Message text: Delivery date &1 of schedule line was adopted as update date
The delivery date &V1& of the schedule line was adopted as the update
date.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
The delivery date of the schedule line is used as the update date
(update of data from PO/delivery schedule).
In some cases, the update date is changed to the start or end date of
the arrangement validity period if the original date is not within the
arrangement validity period (e.g. as a result of a data input error).
In the case of arrangements settled periodically, if the update date
falls in a period for which settlement accounting has already been
performed, business volumes are assigned to the next period for which
settlement accounting is due. The update date is changed accordingly.
This procedure ensures realtime inclusion of business volumes during
subsequent settlement.
Error message extract from SAP system. Copyright SAP SE.
NAA638
- Delivery date &1 of schedule line was adopted as update date ?The SAP error message NAA638 indicates that the delivery date of a schedule line has been adopted as the update date. This typically occurs in the context of sales and distribution (SD) or materials management (MM) when there is a mismatch or issue with the scheduling of deliveries.
Cause:
- Mismatch in Dates: The delivery date specified in the schedule line may not align with the expected or required dates in the system.
- System Configuration: There may be configuration settings in the SAP system that dictate how delivery dates are handled, which could lead to this message if not set correctly.
- Data Entry Errors: Incorrect data entry during the creation or modification of sales orders or purchase orders can lead to this error.
- Dependencies on Other Documents: The delivery date may be influenced by other documents (like production orders or purchase requisitions) that have not been updated or are causing conflicts.
Solution:
- Check Schedule Line Dates: Review the schedule line in question to ensure that the delivery date is correct and aligns with the overall order and delivery plan.
- Update Dates Manually: If the delivery date is incorrect, update it manually in the sales order or purchase order to reflect the correct date.
- Review Configuration Settings: Consult with your SAP configuration team to ensure that the settings related to delivery dates and scheduling are correctly configured.
- Check Related Documents: Investigate any related documents (like production orders or purchase orders) that may be affecting the delivery date and ensure they are updated accordingly.
- Consult SAP Notes: Check the SAP Support Portal for any relevant notes or updates that may address this specific error message.
Related Information:
If the issue persists after following these steps, it may be beneficial to engage with your SAP support team or consult with an SAP expert for further troubleshooting.
Get instant SAP help. Start your 7-day free trial now.
NAA637
Posting date &1 was adopted as the update date
What causes this issue? Posting date &V1& was adopted as the update date.System Response Please look into this matter.How to fix this error?...
NAA636
Document date &1 was adopted as the update date
What causes this issue? The document date &V1& was adopted as the update date.System Response The system issues an error message and will no...
NAA639
Posting/billing date &1 was adopted as update date
What causes this issue? The posting/billing date &V1& was adopted as the update date.System Response The system issues an error message and ...
NAA640
Update date &1 is outside the arrangement period
What causes this issue? Update date &V1& is outside the validity period of arrangement &V2&.System Response The update date is chang...