Do you have any question about this error?
Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 428
Message text: &1: &2 (S9)
The following reasons exist:
Either a component of the planned order or production order entered is
identical to the material that is to be produced on this basis of this
order, or
the low-level code of the component is smaller than the low-level code
of the material produced.
In the first case, recursiveness occurs, in the second case, it is
possible.
To avoid an endless loop, the dependent requirement is not taken into
account. The receipt elements that cover this dependent requirement are
therefore also not displayed in the order report.
Please check the low-level codes of the materials in question.
&ANNOTATION&
This message is only used in the order report and not in the MRP list
or in the current stock/requirements list.
Error message extract from SAP system. Copyright SAP SE.
MD428
- &1: &2 (S9) ?The SAP error message MD428 typically relates to issues in the Material Requirements Planning (MRP) process, specifically concerning the availability of materials or the planning of production orders. The error message format you provided indicates that there are two variables (&1 and &2) that would provide more context about the specific issue.
Cause:
- Material Availability: The error may indicate that the required quantity of a material is not available for the planned production or sales order.
- Planning Parameters: Incorrect planning parameters or settings in the material master data could lead to this error.
- Stock Levels: The stock levels may not meet the requirements due to previous consumption, incorrect stock postings, or unplanned demand.
- MRP Type: The MRP type assigned to the material may not be appropriate for the planning strategy being used.
Solution:
- Check Material Availability: Verify the stock levels of the material in question. Use transaction codes like
MMBE
to check stock status.- Review MRP Settings: Check the MRP settings in the material master (transaction code
MM02
) to ensure they are correctly configured.- Adjust Planning Parameters: If necessary, adjust the planning parameters such as lot size, safety stock, and reorder point.
- Run MRP Again: After making any necessary adjustments, run the MRP process again to see if the error persists.
- Analyze Demand and Supply: Review the demand and supply situation for the material to ensure that all requirements are accounted for.
- Check for Open Purchase Orders: Ensure that there are no open purchase orders that could be affecting the availability of the material.
Related Information:
MD04
(Stock/Requirements List) and MD01
(MRP Run).If the error persists after following these steps, it may be beneficial to consult with your SAP support team or refer to SAP community forums for additional insights.
Get instant SAP help. Start your 7-day free trial now.
MD427
&1: &2 (P4)
What causes this issue? The production finish date calculated using the routing lies after the order finish date that was calculated using the in-hou...
MD426
&1: &2 (P3)
What causes this issue? In Customizing, no specification has been made to allow the adjustment of the order start date to the production start date. ...
MD429
&1: &2 (U6)
What causes this issue? In the individual segment (make-to-order planning, individual project planning, or direct production or direct procurement), ...
MD430
&1: &2 (C1)
What causes this issue? The maximum release quantity of the source of supply for this receipt has been exceeded. In the quota file, you can specify m...