Do you have any question about this error?
Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 429
Message text: &1: &2 (U6)
In the individual segment (make-to-order planning, individual project
planning, or direct production or direct procurement), the total of
stock and receipts is greater than the requirements.
The reason for this is, for example, that the sales order quantity has
been reduced.
The exception message is set by the system as follows:
If stock alone is greater than the requirements in the individual
segment, the exception is displayed in the stock line.
If receipts are scheduled, the exception message is displayed for the
receipts that lie furthest in the future. Here, an exception message is
given to all receipts whose quantities (also partially) exceed the
requirements quantity.
On the details screen for the receipts, the system also displays the
required quantity, not needed to cover the requirement.
The exception message is displayed in the MRP list and in the
stock/requirements list.
Either the stock is to be reduced by stock transfer or the receipts
should be reduced.
Error message extract from SAP system. Copyright SAP SE.
MD429
- &1: &2 (U6) ?The SAP error message MD429 typically indicates an issue related to the availability of materials in the context of demand management or production planning. The message format you provided suggests that it is a specific error related to the availability check for a material.
Cause:
The error message MD429 usually occurs due to one of the following reasons:
- Insufficient Stock: The system cannot find enough stock of the material to fulfill the demand.
- Incorrect Configuration: The material master or the configuration settings for the availability check may not be set up correctly.
- Planning Parameters: The planning parameters for the material may not be correctly defined, leading to issues in availability checks.
- Sales Order or Production Order Issues: There may be issues with the sales orders or production orders that are linked to the material.
Solution:
To resolve the MD429 error, you can take the following steps:
- Check Stock Levels: Verify the stock levels of the material in question. Use transaction codes like
MMBE
(Stock Overview) to check the available stock.- Review Material Master Data: Ensure that the material master data is correctly configured. Check the availability check settings in the material master (transaction code
MM02
).- Check Planning Parameters: Review the planning parameters for the material. Ensure that the lot size, safety stock, and other relevant parameters are set correctly.
- Analyze Demand: Look at the demand for the material. If there are unexpected spikes in demand, consider adjusting the planning or procurement strategies.
- Check Open Orders: Review any open sales orders or production orders that may be consuming the available stock. Use transaction codes like
VA05
(List of Sales Orders) orCO03
(Display Production Order) to check for open orders.- Run MRP: If necessary, run the Material Requirements Planning (MRP) process to generate procurement proposals for the material.
Related Information:
MMBE
, MM02
, MD04
(Stock/Requirements List), and MD01
(MRP Run).If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or refer to SAP community forums for additional insights.
Get instant SAP help. Start your 7-day free trial now.
MD428
&1: &2 (S9)
What causes this issue? The following reasons exist: Either a component of the planned order or production order entered is identical to the material...
MD427
&1: &2 (P4)
What causes this issue? The production finish date calculated using the routing lies after the order finish date that was calculated using the in-hou...
MD430
&1: &2 (C1)
What causes this issue? The maximum release quantity of the source of supply for this receipt has been exceeded. In the quota file, you can specify m...
MD431
&1: &2 (S4)
What causes this issue? A phantom assembly could not be exploded in a BOM explosion for the planned order or the subcontracting purchase requisition....
Click on this link to search all SAP messages.