Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 427
Message text: &1: &2 (P4)
The production finish date calculated using the routing lies after the
order finish date that was calculated using the in-house processing time
in the material master record.
As the system uses the order finish date in the planning run, this
situation may lead to material shortages if production is not finished
until the production finish date calculated by the system.
This exception is displayed in the MRP list and in the current
stock/requirements list.
Check the times in the material master record and in the routing.
Check whether the order has to be rescheduled in.
Error message extract from SAP system. Copyright SAP SE.
MD427
- &1: &2 (P4) ?The SAP error message MD427 typically relates to issues in the Material Requirements Planning (MRP) process, specifically concerning the planning of materials. The message format you provided indicates that it is a warning or error related to the planning run.
Cause: The error message MD427 usually indicates that there is a problem with the planning parameters or the data related to the material being planned. Common causes include: Missing Master Data: The material master data may be incomplete or missing essential information, such as MRP type, lot size, or procurement type. Incorrect MRP Settings: The settings in the MRP view of the material master may not be configured correctly. Planning File Entries: There may be issues with the planning file entries that prevent the system from processing the material correctly. Stock Levels: The stock levels may not meet the requirements for the planned orders, leading to discrepancies. Demand and Supply Mismatch: There may be a mismatch between
Get instant SAP help. Sign up for our Free Essentials Plan.
MD426
&1: &2 (P3)
What causes this issue? In Customizing, no specification has been made to allow the adjustment of the order start date to the production start date. ...
MD425
&1: &2 (P2)
What causes this issue? The system could not find a valid routing when scheduling via the routing or the routing is incorrect.System Response This e...
MD428
&1: &2 (S9)
What causes this issue? The following reasons exist: Either a component of the planned order or production order entered is identical to the material...
MD429
&1: &2 (U6)
What causes this issue? In the individual segment (make-to-order planning, individual project planning, or direct production or direct procurement), ...