How To Fix MD426 - &1: &2 (P3)


MD426 - Overview

  • Message type: E = Error

  • Message class: MD - Material Requirements Planning (MRP)

  • Message number: 426

  • Message text: &1: &2 (P3)

  • Show details Hide details
  • What causes this issue?

    In Customizing, no specification has been made to allow the adjustment
    of the order start date to the production start date.
    However, the production start date calculated using the routing lies
    before the order start date calculated using the in-house processing
    time in the material master record.
    This could mean that the times in the material master record or in the
    routing are incorrect. If the in-house processing time in the material
    master record is too small, this may lead to material shortages.

    System Response

    This exception is displayed in the MRP list and in the current
    stock/requirements list.

    How to fix this error?

    Check the times in the material master record and in the routing.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message MD426 - &1: &2 (P3) ?
    The SAP error message MD426 typically relates to issues in the Material Requirements Planning (MRP) process, specifically concerning the planning of materials. The message format you provided indicates that it is a warning or error related to the planning run.
    
    Cause: The error message MD426 usually indicates that there is a problem with the planning parameters or data for a specific material. Common causes include: Missing Master Data: The material master data may be incomplete or missing essential information, such as MRP type, lot size, or procurement type. Incorrect MRP Settings: The settings in the MRP view of the material master may not be configured correctly. Planning File Entries: There may be issues with the planning file entries that prevent the system from processing the material correctly. Stock Levels: The stock levels may not meet the requirements for the planned orders, leading to discrepancies. Demand and Supply Mismatch: There may be a mismatch between demand and supply,

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:
  • MD425 &1: &2 (P2)
    What causes this issue? The system could not find a valid routing when scheduling via the routing or the routing is incorrect.System Response This e...

  • MD424 &1: &2 (P1)
    What causes this issue? The scheduling data in the Customizing settings are not consistent for the material. Possible reasons, for example: detailed ...

  • MD427 &1: &2 (P4)
    What causes this issue? The production finish date calculated using the routing lies after the order finish date that was calculated using the in-hou...

  • MD428 &1: &2 (S9)
    What causes this issue? The following reasons exist: Either a component of the planned order or production order entered is identical to the material...

Click on this link to search all SAP messages.