How To Fix KJ225 - Planned cost = 0. Cannot use method of apportionment (&,&)


SAP Error Message - Details

  • Message type: E = Error

  • Message class: KJ - Cost Object Controlling for Make-to-Order Production

  • Message number: 225

  • Message text: Planned cost = 0. Cannot use method of apportionment (&,&)

  • Show details Hide details
  • What causes this issue?

    This procedure apportions the <DS:GLOS.results_analysis_data>results
    analysis data</> calculated in <DS:GLOS.results_analysis>results
    analysis</> to the <DS:GLOS.line_ID>line IDs</> in proportion to the
    total planned costs. In this case, however, the planned costs are zero.
    This means the method of apportionment cannot be used.
    The pair (&V1&,&V2&) means (line ID category, results analysis form).
    The line ID categories are:
    K = costs
    P = costs of commissions and complaints
    The results analysis forms are:
    B = work in process
    R = reserves for unrealized costs
    P = reserves for commissions and complaints

    System Response

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    How to fix this error?

    When you press ENTER, the system will attempt to select another method
    of apportionment. The search will use the following sequence:
    Apportionment numbers (based on the apportionment number defined under
    <LS>Define Update for Results Analysis</>)
    Apportionment numbers, with apportionment numbers per line ID = 1
    Only the value of the open period is distributed using the changed
    method.
    You can also go into Customizing under <LS>Define Valuation
    Methods for Results Analysis</> and choose a method of
    apportionment for the selected
    <DS:GLOS.results_analysis_version>results analysis version</>
    that apportions the values differently.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message KJ225 - Planned cost = 0. Cannot use method of apportionment (&,&) ?
    The SAP error message KJ225, which states "Planned cost = 0. Cannot use method of apportionment (&,&)," typically occurs in the context of cost planning and allocation in SAP Controlling (CO) module, particularly when dealing with internal orders, cost centers, or projects.
    
    Cause: Zero Planned Costs: The primary cause of this error is that the planned costs for the cost object (e.g., internal order, cost center, or project) are set to zero. This means that there are no costs available to allocate or apportion using the specified method. Incorrect Configuration: The method of apportionment being used may not be applicable if there are no planned costs to distribute. Data Entry Errors: There may be an oversight in data entry where planned costs were not entered or were inadvertently set to zero.
    Solution: Check Planned Costs: Navigate to the relevant cost object (e.g., internal order, cost center) and verify the planned costs. Ensure that they are correctly

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages: