Do you have any question about this error?
Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 107
Message text: Resource &1 can only be planned under cost element &2
You want to plan resource &V1& under cost element &V4&.
However, in the master record for this resource, you specified for
fiscal year &V3& that the resource may only be planned under cost
element &V2&.
The entry is rejected by the system.
Plan the resource under cost element &V2&, or remove the cost element
from the resource master record.
Error message extract from SAP system. Copyright SAP SE.
K8107
- Resource &1 can only be planned under cost element &2 ?The SAP error message K8107 ("Resource &1 can only be planned under cost element &2") typically occurs in the context of cost planning and resource management within SAP. This error indicates that there is a mismatch between the resource being used and the cost element that is assigned to it. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- Resource Configuration: The resource (e.g., a work center, machine, or labor) is configured to be associated with a specific cost element. If you attempt to plan costs for this resource using a different cost element, the system will trigger this error.
- Cost Element Assignment: The cost element you are trying to use for planning does not match the cost element that is defined for the resource in the system.
- Planning Version: The planning version you are using may not be set up correctly, or it may not include the necessary configurations for the resource and cost element.
Solution:
Check Resource Configuration:
- Go to the resource master data (e.g., work center or production resource) and verify the assigned cost element. Ensure that it matches the cost element you are trying to use for planning.
- If necessary, update the resource configuration to reflect the correct cost element.
Review Cost Element:
- Ensure that the cost element you are trying to use is valid and active in the system. You can check this in the cost element master data.
- If the cost element is incorrect, you may need to change it to the correct one that is associated with the resource.
Planning Version:
- Check the planning version settings to ensure that it is configured correctly for the resources and cost elements you are working with.
- If you are using a specific planning version, make sure it includes the necessary settings for the resources and cost elements.
Consult Documentation:
- Review SAP documentation or help resources related to cost planning and resource management for additional insights and best practices.
Contact Support:
- If the issue persists after checking the above points, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.
Related Information:
CR01
(Create Work Center), CR02
(Change Work Center), or KP06
(Cost Center Planning) to access and modify the relevant data.By following these steps, you should be able to resolve the K8107 error and successfully plan costs for the resource in question.
Get instant SAP help. Start your 7-day free trial now.
K8106
No line items written for the selected key figure
What causes this issue? You want to execute the "Line items" function for key figure &V1&. However, no line items are written for t...
K8105
No activities were planned on cost center &
What causes this issue? You want to display all sender activity types for sender cost center &V1& in fiscal year &V2& in version &...
K8108
Cost element & is locked or has no deletion indicator
What causes this issue? You want to include cost element &V1& in a resource master record. You cannot use this cost element, as it is either ...
K8109
No price could be calculated for resource &1 on cost center &2
What causes this issue? You want to carry out resource planning for resource &V1& on cost center &V2&. In fiscal year &V3&, v...
Click on this link to search all SAP messages.