Do you have any question about this error?
Message type: E = Error
Message class: HRPAYFR_PY - Payroll Functions message class
Message number: 038
Message text: CTT: Start date &2 of the contract &1 is prior to the hiring date &3
The start date &V2& of the contract &V1& of the employee (infotype 0016
- Contract Elements, INBEG field of infotype view 3316) is prior to the
record start date of the infotype 0016 and the hiring date of the
infotype 0000 - Actions &V3&.
This situation may occur if the initial hiring date was corrected at a
later date. If the transaction PA40 was used to make this change, the
contract start date (P3316-INBEG) is not necessarily modified
automatically, unlike the validity dates of the infotype 0016. In this
case, the user must explicitly change the contract start date, if
applicable.
The system returns an error message.
Check the contract start date and the hiring action of the employee;
otherwise, correct the contract start date so that it falls in line with
the employee?s hiring date.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
HRPAYFR_PY038
- CTT: Start date &2 of the contract &1 is prior to the hiring date &3 ?The SAP error message HRPAYFR_PY038 indicates that there is a discrepancy between the start date of a contract and the hiring date of an employee. Specifically, the error states that the start date of the contract (represented as &2) is earlier than the hiring date (represented as &3) for the contract (represented as &1). This situation typically arises in the context of payroll processing or employee data management in SAP HR (Human Resources).
Cause:
- Incorrect Data Entry: The start date of the contract may have been entered incorrectly, leading to it being set before the actual hiring date of the employee.
- Data Migration Issues: If data was migrated from another system, there may have been inconsistencies or errors in the data transfer.
- Contract Changes: If there were changes made to the contract dates after the employee was hired, it could lead to this error if the new start date is earlier than the hiring date.
Solution:
- Verify Dates: Check the contract start date and the hiring date in the employee's master data. Ensure that the contract start date is not earlier than the hiring date.
- Correct Data: If the contract start date is incorrect, update it to a date that is on or after the hiring date.
- Review Contract Changes: If there have been recent changes to the contract, ensure that all related dates are consistent and correctly reflect the intended timeline.
- Consult with HR: If you are unsure about the correct dates, consult with your HR department or the person responsible for employee records to clarify the correct information.
Related Information:
By addressing the discrepancies in the dates, you should be able to resolve the error and proceed with the payroll processing or any other related HR activities.
Get instant SAP help. Start your 7-day free trial now.
HRPAYFR_PY037
Contract &1 with start &2 must be defined with a new contract reference
What causes this issue? A record exists in infotype 16 that starts at the contract start date. However, this record was entered without a new contrac...
HRPAYFR_PY036
Contract of personnel number &1 must be defined with start date &2
What causes this issue? You maintain a contract for the personnel number with infotype 0001, but you do not have the record corresponding to the new ...
HRPAYFR_PY039
CTT_END: Value &1 in FIMOD field is not consistent for termin. reason &2
What causes this issue? You have performed the following operations: Entry of the value &V2& in the <ZH>FIMOT</> field <LS>...
HRPAYFR_PY040
CTT: personnel number &1, on &2, field &3 required
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.