How To Fix HRHAP00_PMP_PROCESS018 - The total of the goal distribution values must equal either 100% or 0%


SAP Error Message - Details

  • Message type: E = Error

  • Message class: HRHAP00_PMP_PROCESS - Message Class for Performance Management Process

  • Message number: 018

  • Message text: The total of the goal distribution values must equal either 100% or 0%

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message HRHAP00_PMP_PROCESS018 - The total of the goal distribution values must equal either 100% or 0% ?

    The SAP error message HRHAP00_PMP_PROCESS018 indicates that there is an issue with the goal distribution values in the Performance Management module. Specifically, the error states that the total of the goal distribution values must equal either 100% or 0%. This typically occurs during the performance appraisal process when the distribution of goals assigned to an employee does not meet the required criteria.

    Cause:

    1. Incorrect Goal Distribution: The sum of the percentages assigned to the individual goals does not equal 100% or is not set to 0%. This can happen if:

      • Some goals are assigned a percentage, but the total does not add up to 100%.
      • There are goals with assigned percentages, but the user has not completed the distribution correctly.
      • There are missing values or incorrectly entered values in the goal distribution fields.
    2. Configuration Issues: There may be configuration settings in the SAP system that enforce this rule, and if the settings are not aligned with the business process, it can lead to this error.

    Solution:

    1. Check Goal Distribution Values:

      • Navigate to the goal-setting screen where the goals are defined.
      • Review the distribution values assigned to each goal.
      • Ensure that the total of all goal distribution values equals 100% or is set to 0% if no goals are assigned.
    2. Adjust Values:

      • If the total is not correct, adjust the individual goal percentages accordingly.
      • If you have goals that should not be included, consider setting their distribution to 0%.
    3. Validation:

      • After making adjustments, validate the entries to ensure that the total is now correct.
      • Save the changes and attempt to process the performance appraisal again.
    4. Consult Documentation: If the issue persists, refer to SAP documentation or help resources for further guidance on goal distribution settings.

    5. System Configuration: If you suspect a configuration issue, consult with your SAP administrator or technical team to review the settings related to performance management and goal distribution.

    Related Information:

    • SAP Notes: Check for any relevant SAP Notes that may address this specific error or provide additional troubleshooting steps.
    • User Training: Ensure that users involved in the performance management process are trained on how to correctly enter and manage goal distributions.
    • Testing: If changes are made to the configuration, conduct thorough testing in a development or quality assurance environment before applying changes to the production system.

    By following these steps, you should be able to resolve the error and ensure that the goal distribution values are correctly set in the SAP system.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant