Do you have any question about this error?
Message type: E = Error
Message class: FCO_AVC_CC - Availability Control: Cost Centers
Message number: 004
Message text: Cost center &1 isn't considered because profile wasn't specified.
You have specified budget-carrying cost center &V1& for cost center &V1&
. However, you haven't specified the <LS>Budget Availability Control
Profile</>.
A budget availability control profile is necessary for both budget
availability control and budget reporting. Therefore, without a profile,
cost center &V1& isn't considered in the cost center budget report, nor
in budget availability control.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
You can either specify a <LS>Budget Availability Control Profile</> or
you can remove the budget-carrying cost center.
Note: You can only specify a budget availability control profile for
cost centers, which are also budget-carrying cost centers.
Error message extract from SAP system. Copyright SAP SE.
FCO_AVC_CC004
- Cost center &1 isn't considered because profile wasn't specified. ?The SAP error message FCO_AVC_CC004 indicates that a cost center is not being considered in a particular transaction or process because a profile was not specified for it. This error typically arises in the context of Activity-Based Costing (ABC) or when using the Availability Control (AVC) functionality in SAP.
Cause:
- Missing Profile Assignment: The cost center in question does not have a profile assigned to it. Profiles are used to define how costs are controlled and monitored.
- Configuration Issues: There may be a configuration issue in the system where the cost center is not properly set up to be included in the relevant processes.
- Transaction Settings: The specific transaction or process being executed may require a profile that has not been defined for the cost center.
Solution:
Assign a Profile:
- Go to the configuration settings for the cost center in SAP.
- Ensure that a valid profile is assigned to the cost center. This can typically be done in the Cost Center Master Data (Transaction code: KS01 or KS02).
- Check the settings under the "Control" tab to see if a profile is specified.
Review Configuration:
- Check the configuration for Availability Control (Transaction code: SPRO).
- Navigate to Controlling > Cost Center Accounting > Planning > Define Availability Control and ensure that the necessary profiles are defined and assigned correctly.
Check Transaction Settings:
- Review the transaction or process that is generating the error to ensure that it is set up to use the correct profiles for cost centers.
Consult Documentation:
- Refer to SAP documentation or help resources for more detailed guidance on setting up cost centers and profiles.
Testing:
- After making the necessary changes, test the transaction again to ensure that the error is resolved.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in Controlling and Availability Control.
Get instant SAP help. Start your 7-day free trial now.
FCO_AVC_CC003
Specify a profile for budget-carrying cost centers only.
What causes this issue? For cost center &V2&, you have specified a budget-carrying cost center &v1& and a budget availability control...
FCO_AVC_CC002
Specify the budget availability control profile for cost center &1.
What causes this issue? For cost center &V1&, you have activated <LS>Budget Availability Control </>. However, you haven't s...
FCO_AVC_CC005
Budget availability control is inactive for cost center &1.
What causes this issue? You have defined cost center &V1& as a budget-carrying cost center<(> ,<)> and you have specified a <L...
FCO_AVC_CC006
Company codes differ for cost ctr &1 and budget-carrying cost ctr &2.
What causes this issue? Company codes differ for cost center &V1& and budget-carrying cost center &V2&. The company code for cost cen...
Click on this link to search all SAP messages.