Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 209
Message text: You cannot change &1 '&2'
&V1& '&V2&' is opened in display mode only, or its status does not
allow you to make changes.
The system does not carry out scheduling.
Switch to the change mode or check the status of the project element.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED209
- You cannot change &1 '&2' ?The SAP error message DPR_SHARED209, which states "You cannot change &1 '&2'," typically occurs in the context of project management within the SAP system, particularly when dealing with project definitions, work breakdown structures (WBS), or project planning elements.
Cause: This error usually arises due to one of the following reasons: Status Restrictions: The project or WBS element you are trying to change may be in a status that does not allow modifications. For example, if the project is completed or locked, changes will not be permitted. Authorization Issues: The user may not have the necessary authorizations to make changes to the specified project or WBS element. Project Type Restrictions: Certain project types may have restrictions on modifications based on their configuration or business rules. Dependencies: There may be dependencies or relationships with other project elements that prevent changes.
Solution: To resolve the error, consider the following steps: Check Project Status: Verify the status of the project or WBS element.
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED208
&1 &2: Dates are outside the validity period of the calendar
What causes this issue? If you schedule &V1& '&V2&', it would have dates that lie outside of the validity period of the cal...
DPR_SHARED207
Links create a cycle; you cannot schedule
What causes this issue? The links form a <ZH>loop</>; scheduling is not possible.System Response The links between the project elements ...
DPR_SHARED210
You require authorization to schedule &1 '&2'
What causes this issue? You do not have sufficient authorization to carry out scheduling for &V1& '&V2&'.System Response T...
DPR_SHARED211
&1 &2: Start constraint conflicts with determined start
What causes this issue? A constraint is set for the start of the project element. In forward scheduling, the system calculates the start (earliest st...