Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 208
Message text: &1 &2: Dates are outside the validity period of the calendar
If you schedule &V1& '&V2&', it would have dates that lie outside of
the validity period of the calendar.
The system does not carry out scheduling.
Check the set dates and duration of the project elements for their
correctness.
If the dates are correct then extend the validity period of the factory
calendar.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED208
- &1 &2: Dates are outside the validity period of the calendar ?The SAP error message DPR_SHARED208 indicates that the dates you are trying to use in a project or planning scenario are outside the validity period of the calendar defined for that project. This typically occurs in the context of project management or planning modules, such as SAP Project System (PS) or SAP Portfolio and Project Management (PPM).
Cause: Invalid Date Range: The start and/or end dates of the project or task you are trying to create or modify fall outside the defined validity period of the calendar assigned to that project. Calendar Settings: The calendar associated with the project may have specific start and end dates that do not encompass the dates you are trying to use. Project Configuration: The project or task may be configured with a calendar that is not appropriate for the dates being used.
Solution: Check Calendar Validity: Go to the calendar settings in your SAP system and verify the validity period of
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED207
Links create a cycle; you cannot schedule
What causes this issue? The links form a <ZH>loop</>; scheduling is not possible.System Response The links between the project elements ...
DPR_SHARED206
&1 &2: Start constraint conflicts with a successor date
What causes this issue? When backward scheduling the project element, the system calculated a start date based on a successor relationship and the du...
DPR_SHARED209
You cannot change &1 '&2'
What causes this issue? &V1& '&V2&' is opened in display mode only, or its status does not allow you to make changes.System...
DPR_SHARED210
You require authorization to schedule &1 '&2'
What causes this issue? You do not have sufficient authorization to carry out scheduling for &V1& '&V2&'.System Response T...