Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 206
Message text: &1 &2: Start constraint conflicts with a successor date
When backward scheduling the project element, the system calculated a
start date based on a successor relationship and the duration of the
project element. This start date occurs before the fixed start of the
project element.
The system ignores the successor relationship and defines the fixed
start date as the calculated start of the project element. The system
calculates the finish date from that point onwards using the duration of
the project element.
Check whether the fixed start date is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED206
- &1 &2: Start constraint conflicts with a successor date ?The SAP error message DPR_SHARED206 indicates that there is a conflict with the scheduling of tasks in a project, specifically related to start constraints and successor dates. This error typically arises in the context of project management within SAP, particularly when using the Project System (PS) or the Project Management (PM) module.
Cause:
The error occurs when:
To resolve the DPR_SHARED206 error, you can take the following steps:
Check Task Dependencies:
Adjust Start Constraints:
Modify Task Dates:
Review Project Scheduling Settings:
Use the Scheduling Tool:
Consult Documentation:
CJ20N
(Project Builder) or CJ02
(Change Project) to view and modify project tasks and their dependencies.By following these steps, you should be able to identify the source of the conflict and implement a solution to resolve the error.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED205
&1 &2: Finish constraint conflicts with a predecessor date
What causes this issue? When forward scheduling the project element, the system calculated a finish date based on a predecessor relationship and the ...
DPR_SHARED204
&1 &2: Finish constraint conflicts with duration
What causes this issue? The system calculated a finish date from the start date and duration when scheduling the project element. This finish date co...
DPR_SHARED207
Links create a cycle; you cannot schedule
What causes this issue? The links form a <ZH>loop</>; scheduling is not possible.System Response The links between the project elements ...
DPR_SHARED208
&1 &2: Dates are outside the validity period of the calendar
What causes this issue? If you schedule &V1& '&V2&', it would have dates that lie outside of the validity period of the cal...
Click on this link to search all SAP messages.