Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 205
Message text: &1 &2: Finish constraint conflicts with a predecessor date
When forward scheduling the project element, the system calculated a
finish date based on a predecessor relationship and the duration of the
project element. This finish date occurs after the fixed finish of the
project element.
The system ignores the predecessor relationship and defines the fixed
finish date as the calculated finish of the project element. The system
calculates the start date by using the finish date and subtracting the
duration of the project element from it.
Check whether the fixed finish date of the project element is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED205
- &1 &2: Finish constraint conflicts with a predecessor date ?The SAP error message DPR_SHARED205 indicates that there is a conflict with a finish constraint in a project, specifically that the finish date of a task is conflicting with the start date of its predecessor task. This typically occurs in project management scenarios where tasks are linked with dependencies, and the scheduling of these tasks does not align correctly due to constraints.
Cause: Finish Constraint: The task has a finish constraint that is set to a date that is earlier than the start date of its predecessor task. Predecessor Relationship: The predecessor task has not been completed or is scheduled to finish later than the required start date of the dependent task. Incorrect Dates: The dates assigned to tasks may have been entered incorrectly, leading to conflicts. Task Dependencies: The dependencies between tasks may not be set up correctly, causing scheduling conflicts.
Solution: Check Task Dates: Review the start and finish dates of both the task that
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED204
&1 &2: Finish constraint conflicts with duration
What causes this issue? The system calculated a finish date from the start date and duration when scheduling the project element. This finish date co...
DPR_SHARED203
&1 &2: Start constraint conflicts with duration
What causes this issue? The system calculated a start date from the finish date and duration when scheduling the project element. This start date con...
DPR_SHARED206
&1 &2: Start constraint conflicts with a successor date
What causes this issue? When backward scheduling the project element, the system calculated a start date based on a successor relationship and the du...
DPR_SHARED207
Links create a cycle; you cannot schedule
What causes this issue? The links form a <ZH>loop</>; scheduling is not possible.System Response The links between the project elements ...
Click on this link to search all SAP messages.