Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 203
Message text: &1 &2: Start constraint conflicts with duration
The system calculated a start date from the finish date and duration
when scheduling the project element. This start date conflicts with the
start date of the start constraint.
The system sets the start date of the start constraint as the calculated
start of the project element and recalculates the finish date for the
project element from the duration as necessary.
Check whether the start constraint of the project element is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED203
- &1 &2: Start constraint conflicts with duration ?The SAP error message DPR_SHARED203 typically occurs in the context of project management within SAP, particularly when dealing with project planning and scheduling in the SAP Project System (PS) or SAP Portfolio and Project Management (PPM) modules. This error indicates that there is a conflict between the start constraint of a task and its duration, which prevents the task from being scheduled correctly.
Cause: The error arises when: Start Constraint: A task has a defined start constraint (e.g., "Must Start On," "Start No Earlier Than," or "Start No Later Than") that conflicts with the task's duration. Duration: The duration of the task is such that, given the start constraint, it cannot be completed within the allowed time frame. Dependencies: There may be dependencies with other tasks that further complicate the scheduling. Resource Availability: Resource constraints may also play a role, where the resources required for the task are not available during the scheduled time.
Solution: To resolve the
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED202
&1 &2: Finish constraint conflicts with a successor's date
What causes this issue? A constraint is set for the finish of the project element. During backwards scheduling for the project element, the system ca...
DPR_SHARED201
&1 &2: Start constraint conflicts with a predecessor's date
What causes this issue? A constraint is set for the start of the project element. During forward scheduling for the project element, the system calcu...
DPR_SHARED204
&1 &2: Finish constraint conflicts with duration
What causes this issue? The system calculated a finish date from the start date and duration when scheduling the project element. This finish date co...
DPR_SHARED205
&1 &2: Finish constraint conflicts with a predecessor date
What causes this issue? When forward scheduling the project element, the system calculated a finish date based on a predecessor relationship and the ...