How To Fix DPR_SHARED202 - &1 &2: Finish constraint conflicts with a successor's date


DPR_SHARED202 - Overview

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 202

  • Message text: &1 &2: Finish constraint conflicts with a successor's date

  • Show details Hide details
  • What causes this issue?

    A constraint is set for the finish of the project element.
    During backwards scheduling for the project element, the system
    calculates a finish date from the successor relationships. The system
    compares the determined finish date (latest finish) with the constraint
    for the finish date. The warning appears if the finish date conflicts
    with the constraint for the finish date.

    System Response

    The system ignores the successor relationships and sets the finish date
    of the constraint as the calculated finish.

    How to fix this error?

    Check whether the constraint for the finish date is realistic.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message DPR_SHARED202 - &1 &2: Finish constraint conflicts with a successor's date ?
    The SAP error message DPR_SHARED202 indicates that there is a conflict with the finish constraint of a task in a project. Specifically, it means that the finish date constraint of a predecessor task is conflicting with the start date of a successor task. This typically occurs in project management scenarios where tasks are linked with dependencies, and the scheduling of one task affects another.
    
    Cause: Finish Constraint: The predecessor task has a finish constraint that does not allow it to finish on or before the start date of the successor task. Task Dependencies: The relationship between the predecessor and successor tasks (e.g., Finish-to-Start, Start-to-Start) is not properly aligned with the defined dates. Manual Date Adjustments: If dates have been manually adjusted for either task, it may lead to conflicts with the defined constraints. Project Calendar: The project calendar settings may also affect the scheduling of tasks, leading to conflicts.
    Solution: Check Task Dependencies: Review the dependencies between

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker