Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 202
Message text: &1 &2: Finish constraint conflicts with a successor's date
A constraint is set for the finish of the project element.
During backwards scheduling for the project element, the system
calculates a finish date from the successor relationships. The system
compares the determined finish date (latest finish) with the constraint
for the finish date. The warning appears if the finish date conflicts
with the constraint for the finish date.
The system ignores the successor relationships and sets the finish date
of the constraint as the calculated finish.
Check whether the constraint for the finish date is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED202
- &1 &2: Finish constraint conflicts with a successor's date ?The SAP error message DPR_SHARED202 indicates that there is a conflict with the finish constraint of a task in a project. Specifically, it means that the finish date constraint of a predecessor task is conflicting with the start date of a successor task. This typically occurs in project management scenarios where tasks are linked with dependencies, and the scheduling of one task affects another.
Cause: Finish Constraint: The predecessor task has a finish constraint that does not allow it to finish on or before the start date of the successor task. Task Dependencies: The relationship between the predecessor and successor tasks (e.g., Finish-to-Start, Start-to-Start) is not properly aligned with the defined dates. Manual Date Adjustments: If dates have been manually adjusted for either task, it may lead to conflicts with the defined constraints. Project Calendar: The project calendar settings may also affect the scheduling of tasks, leading to conflicts.
Solution: Check Task Dependencies: Review the dependencies between
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED201
&1 &2: Start constraint conflicts with a predecessor's date
What causes this issue? A constraint is set for the start of the project element. During forward scheduling for the project element, the system calcu...
DPR_SHARED200
*** Scheduling Messages ***
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED203
&1 &2: Start constraint conflicts with duration
What causes this issue? The system calculated a start date from the finish date and duration when scheduling the project element. This start date con...
DPR_SHARED204
&1 &2: Finish constraint conflicts with duration
What causes this issue? The system calculated a finish date from the start date and duration when scheduling the project element. This finish date co...