Do you have any question about this error?
Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 201
Message text: &1 &2: Start constraint conflicts with a predecessor's date
A constraint is set for the start of the project element.
During forward scheduling for the project element, the system calculates
a start date from the predecessor relationships. The system compares the
determined start date (earliest start) with the constraint for the start
date. The warning appears if the start date conflicts with the
constraint for the start date.
The system ignores the predecessor relationship and sets the fixed start
date of the project element as the calculated start.
Check whether the fixed start date is realistic.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED201
- &1 &2: Start constraint conflicts with a predecessor's date ?The SAP error message DPR_SHARED201 indicates that there is a conflict with the start date of a task in a project due to a predecessor's date constraint. This typically occurs in the context of project management within SAP, particularly when using the SAP Project System (PS) or SAP Portfolio and Project Management (PPM) modules.
Cause:
The error arises when:
To resolve this error, you can take the following steps:
Check Task Dependencies:
Adjust Dates:
Review Constraints:
Recalculate Dates:
Check for Manual Changes:
Consult Documentation:
By following these steps, you should be able to resolve the DPR_SHARED201 error and ensure that your project tasks are scheduled correctly.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED200
*** Scheduling Messages ***
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED110
User group &1 already exists
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED202
&1 &2: Finish constraint conflicts with a successor's date
What causes this issue? A constraint is set for the finish of the project element. During backwards scheduling for the project element, the system ca...
DPR_SHARED203
&1 &2: Start constraint conflicts with duration
What causes this issue? The system calculated a start date from the finish date and duration when scheduling the project element. This start date con...