Message text: BAdI DPR_PROJ_INTEGRATION was not implemented
The BAdI <ZK>Change Project Plan Data in Project Management and
Microsoft Project</> (DPR_MSP_CUST_FIELDS) was not implemented in your
system. You can use this BAdI to override the standard import and export
functions in SAP Portfolio and Project Management. This BAdI is called,
for example, when a user imports an MS Project to Project Management.
For more information, see Customizing for <ZK>SAP Portfolio and Project
Management</> under <ZK>Common Functions </>-> <ZK>Import and Export of
Project Data</> -> <ZK>Microsoft Project Integration </>-> <ZK>BAdI:
Change Project Plan Data in Project Management and Microsoft Project.</>
If the BAdI for setting the project integration options was not
implemented, the system issues this message.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_PROJ_INTEGRATION270
- BAdI DPR_PROJ_INTEGRATION was not implemented ?The SAP error message DPR_PROJ_INTEGRATION270 indicates that the Business Add-In (BAdI) DPR_PROJ_INTEGRATION has not been implemented in your SAP system. This BAdI is typically used for project integration scenarios, allowing for custom logic to be executed during project-related processes.
Cause:
The error occurs because the system is trying to execute a piece of code that relies on the BAdI implementation, but no implementation has been defined. This can happen in various scenarios, such as when integrating project management with other modules or when specific project-related functionalities are being called that require custom logic.
Solution:
To resolve this error, you need to implement the BAdI DPR_PROJ_INTEGRATION. Here are the steps to do so:
Access the BAdI Implementation:
- Go to transaction code SE18 (BAdI Definition) or SE19 (BAdI Implementation).
- In SE18, enter the BAdI name
DPR_PROJ_INTEGRATION
and check if there are any existing implementations.Create a New Implementation:
- If no implementation exists, you can create one by going to SE19.
- Click on "Create" and enter a name for your implementation.
- Implement the necessary methods as per your business requirements. You may need to refer to the documentation or consult with your functional team to understand what logic needs to be added.
Activate the Implementation:
- After implementing the required logic, make sure to activate the BAdI implementation.
Testing:
- Test the functionality that was causing the error to ensure that the implementation works as expected and that the error no longer occurs.
Related Information:
By following these steps, you should be able to resolve the error and implement the necessary logic for the BAdI.
Get instant SAP help. Start your 7-day free trial now.
DPR_PROJ_INTEGRATION266
Resource &1 not assigned to any role
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_PROJ_INTEGRATION265
Resource &1 not assigned to any role
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_PROJ_INTEGRATION271
Project &1 is already linked
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_PROJ_INTEGRATION272
Portfolio item does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.