Message type: E = Error
Message class: DPR_ENTITY_LINK - Roles: Messages
Message number: 003
Message text: Task assignment: Finish is before start
The finish date is before the start date for the task assignment between
role/resource &V1& and task &V2&: &V3&
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Check and correct the start and finish dates of the task assignment.
Error message extract from SAP system. Copyright SAP SE.
DPR_ENTITY_LINK003
- Task assignment: Finish is before start ?The SAP error message DPR_ENTITY_LINK003 indicates that there is a problem with the scheduling of tasks in a project. Specifically, it means that the finish date of a task is set to be before its start date, which is logically incorrect and violates the scheduling rules in SAP Project Management.
Cause:
- Incorrect Dates: The most common cause is that the finish date of a task has been entered incorrectly, either manually or through a data import.
- Dependencies: If there are dependencies between tasks, the finish date of a predecessor task may not align correctly with the start date of a successor task.
- Time Zone Issues: Sometimes, time zone settings can lead to discrepancies in date and time calculations.
- Data Migration Issues: If data has been migrated from another system, there may be inconsistencies in date formats or values.
Solution:
- Check Task Dates: Review the start and finish dates of the task in question. Ensure that the finish date is not earlier than the start date.
- Adjust Dependencies: If the task is dependent on another task, check the finish date of the predecessor task and adjust it if necessary.
- Correct Data Entry: If the dates were entered manually, correct any mistakes in the date fields.
- Review Time Zones: Ensure that the time zone settings in your SAP system are correct and consistent.
- Re-evaluate Task Relationships: If the task relationships (dependencies) are not set correctly, adjust them to reflect the correct sequence of tasks.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing task assignments and dependencies.
Related Information:
By following these steps, you should be able to resolve the DPR_ENTITY_LINK003 error and ensure that your project scheduling is accurate.
Get instant SAP help. Start your 7-day free trial now.
DPR_ENTITY_LINK002
Work of task assignment is too high for available working time
What causes this issue? The work defined for the task assignment between role or resource &V1& and task &V2& is higher than the maxim...
DPR_DOCUMENT140
Error occurred when generating the print preview (function module: &1)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_ENTITY_LINK004
Target object for role is unknown
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_ENTITY_LINK005
Task assignment is not within the validity of the role
What causes this issue? The validity &V3& for the task assignment between role/resource &V1& and task &V2& is (partly) outsid...
Click on this link to search all SAP messages.