Message text: & has no connection with successor & in res. netw. struct. & in plant &
The header data of the process order specifies that the operations must
be scheduled on a particular resource network structure.
However, the operation has been scheduled on a resource that is not
defined as a predecessor resource of the resource on which a "successor"
operation is to be carried out.
Please schedule the operations in the sequence defined by the resource
network structure.
Error message extract from SAP system. Copyright SAP SE.
CY727
- & has no connection with successor & in res. netw. struct. & in plant & ?The SAP error message CY727 typically indicates an issue related to the network structure in a project or production order. Specifically, it suggests that there is no connection between the predecessor and successor activities in a network, which can lead to problems in scheduling and resource allocation.
Cause:
- Missing Connections: The error arises when there are no defined relationships (dependencies) between the predecessor and successor activities in the network. This can happen if the network was not set up correctly or if changes were made that removed these connections.
- Incorrect Configuration: The network structure may not be configured properly, leading to disconnections between tasks.
- Plant Assignment Issues: The error may also be related to the plant assignment, where the activities are not correctly linked to the relevant plant or location.
Solution:
Check Network Structure: Review the network structure in the project or order. Ensure that all activities have the necessary predecessor and successor relationships defined.
- Go to the network in question and check the activity relationships.
- Use transaction codes like
CN21
(Create Network) orCN22
(Change Network) to inspect and modify the network structure.Define Relationships: If relationships are missing, you can define them by:
- Adding predecessor and successor relationships between the activities.
- Ensuring that the correct type of relationship (Finish-to-Start, Start-to-Start, etc.) is used based on the project requirements.
Check Plant Assignments: Ensure that all activities are correctly assigned to the relevant plant. If there are discrepancies, correct the plant assignments in the network activities.
Recheck Resource Allocation: Make sure that resources are correctly allocated to the activities and that there are no conflicts that could lead to disconnections.
Consult Documentation: If the issue persists, refer to SAP documentation or consult with your SAP support team for further troubleshooting.
Related Information:
CN01
(Create Network), CN02
(Change Network), and CN03
(Display Network) for managing networks.By following these steps, you should be able to resolve the CY727 error and ensure that your project or production order network is correctly configured.
Get instant SAP help. Start your 7-day free trial now.
CY726
& has no connection with predecessor & in res. netw. struct. & in plant &
What causes this issue? The header data of the process order specifies that the operations must be scheduled on a particular resource network structu...
CY725
& does not belong to resource network structure & in plant &
What causes this issue? The header data of the process order specifies that the operations on resource network structure &V2& are to be sched...
CY728
Order & operation &: Minimum overlap with predecessor & not achieved
What causes this issue? On dispatching an operation the system does not adhere to the minimum overlap time with the preceding operation. There was in...
CY729
Order & operation &: Minimum overlap with successor & not achieved
What causes this issue? When dispatching an operation the system does not adhere to the minimum overlap time with the following operation. There was ...
Click on this link to search all SAP messages.