Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 727
Message text: & has no connection with successor & in res. netw. struct. & in plant &
The header data of the process order specifies that the operations must
be scheduled on a particular resource network structure.
However, the operation has been scheduled on a resource that is not
defined as a predecessor resource of the resource on which a "successor"
operation is to be carried out.
Please schedule the operations in the sequence defined by the resource
network structure.
Error message extract from SAP system. Copyright SAP SE.
CY727
- & has no connection with successor & in res. netw. struct. & in plant & ?The SAP error message CY727 typically indicates an issue related to the network structure in a project or production order. Specifically, it suggests that there is no connection between the predecessor and successor activities in a network, which can lead to problems in scheduling and resource allocation.
Cause: Missing Connections: The error arises when there are no defined relationships (dependencies) between the predecessor and successor activities in the network. This can happen if the network was not set up correctly or if changes were made that removed these connections. Incorrect Configuration: The network structure may not be configured properly, leading to disconnections between tasks. Plant Assignment Issues: The error may also be related to the plant assignment, where the activities are not correctly linked to the relevant plant or location.
Solution: Check Network Structure: Review the network structure in the project or order. Ensure that all activities have the necessary predecessor and successor relationships defined. Go to
Get instant SAP help. Sign up for our Free Essentials Plan.
CY726
& has no connection with predecessor & in res. netw. struct. & in plant &
What causes this issue? The header data of the process order specifies that the operations must be scheduled on a particular resource network structu...
CY725
& does not belong to resource network structure & in plant &
What causes this issue? The header data of the process order specifies that the operations on resource network structure &V2& are to be sched...
CY728
Order & operation &: Minimum overlap with predecessor & not achieved
What causes this issue? On dispatching an operation the system does not adhere to the minimum overlap time with the preceding operation. There was in...
CY729
Order & operation &: Minimum overlap with successor & not achieved
What causes this issue? When dispatching an operation the system does not adhere to the minimum overlap time with the following operation. There was ...