Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 728
Message text: Order & operation &: Minimum overlap with predecessor & not achieved
On dispatching an operation the system does not adhere to the minimum
overlap time with the preceding operation. There was insufficient
available capacity at the desired time.
Increase the available capacity in the time interval in question or
reschedule the preceding operation.
Error message extract from SAP system. Copyright SAP SE.
CY728
- Order & operation &: Minimum overlap with predecessor & not achieved ?The SAP error message CY728 ("Order & operation &: Minimum overlap with predecessor & not achieved") typically occurs in the context of production planning and scheduling within SAP's Advanced Planning and Optimization (APO) or Production Planning (PP) modules. This error indicates that the scheduling of an operation does not meet the required minimum overlap with its predecessor operation.
Cause: Scheduling Constraints: The operation you are trying to schedule has a defined minimum overlap with its predecessor operation, which is not being met. This can happen if: The start time of the current operation is too far in the future compared to the end time of the predecessor operation. The duration of the predecessor operation is longer than expected, causing a scheduling conflict. Configuration Settings: The minimum overlap requirement may be set in the routing or in the production version for the material. If the overlap is not configured correctly, it can lead to this error. Resource
Get instant SAP help. Sign up for our Free Essentials Plan.
CY727
& has no connection with successor & in res. netw. struct. & in plant &
What causes this issue? The header data of the process order specifies that the operations must be scheduled on a particular resource network structu...
CY726
& has no connection with predecessor & in res. netw. struct. & in plant &
What causes this issue? The header data of the process order specifies that the operations must be scheduled on a particular resource network structu...
CY729
Order & operation &: Minimum overlap with successor & not achieved
What causes this issue? When dispatching an operation the system does not adhere to the minimum overlap time with the following operation. There was ...
CY730
Order & operation & and element were deallocated
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.