Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 726
Message text: & has no connection with predecessor & in res. netw. struct. & in plant &
The header data of the process order specifies that the operations must
be scheduled on a particular resource network structure.
However, the operation has been scheduled on a resource that is not
defined as the successor resource of the resource on which a
"predecessor" operation is to be carried out.
Please schedule the operations in the sequence defined by the resource
network structure.
Error message extract from SAP system. Copyright SAP SE.
CY726
- & has no connection with predecessor & in res. netw. struct. & in plant & ?The SAP error message CY726 typically indicates an issue related to the network structure in a project or production planning context. This error suggests that there is a problem with the relationship between activities in a network, specifically that a certain activity has no connection with its predecessor in the network structure.
Cause:
- Missing Predecessor Relationship: The activity in question is expected to have a predecessor, but it does not. This can happen if the predecessor activity was deleted or if the relationship was not properly defined.
- Incorrect Network Configuration: The network structure may not be set up correctly, leading to disconnections between activities.
- Data Integrity Issues: There may be inconsistencies in the data, such as missing or incorrect entries in the network or activity definitions.
Solution:
Check Activity Relationships:
- Go to the network in question and check the relationships between activities. Ensure that all activities have the correct predecessor and successor relationships defined.
- If an activity is missing a predecessor, you may need to add one manually.
Review Network Structure:
- Open the network structure in the SAP system and verify that all activities are correctly linked. Look for any activities that are isolated or not connected to the main flow.
- If necessary, recreate the network or adjust the existing one to ensure proper connections.
Data Validation:
- Perform a data validation check to ensure that all entries related to the network and activities are correct and complete.
- Check for any inconsistencies or missing data that could be causing the issue.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on network structures and activity relationships.
SAP Notes and Support:
- Check the SAP Support Portal for any relevant notes or patches that may address this specific error message.
- If the issue persists, consider reaching out to SAP support for further assistance.
Related Information:
CN21
(Create Network), CN22
(Change Network), or CN41
(Display Network) to manage and review network structures.By following these steps, you should be able to identify and resolve the issue related to the CY726 error message in SAP.
Get instant SAP help. Start your 7-day free trial now.
CY725
& does not belong to resource network structure & in plant &
What causes this issue? The header data of the process order specifies that the operations on resource network structure &V2& are to be sched...
CY724
Order & operation & begins in the past
What causes this issue? The system is to dispatch an operation. The indicator <ZH>Indicator forwards</> is not set in the strategy profil...
CY727
& has no connection with successor & in res. netw. struct. & in plant &
What causes this issue? The header data of the process order specifies that the operations must be scheduled on a particular resource network structu...
CY728
Order & operation &: Minimum overlap with predecessor & not achieved
What causes this issue? On dispatching an operation the system does not adhere to the minimum overlap time with the preceding operation. There was in...
Click on this link to search all SAP messages.