Message type: E = Error
Message class: CRM_LEASING_CHANGE - Messages for Changes to Leases
Message number: 162
Message text: Different start date for contract split
The start date of item change process number &V1& (process &V2&) differs
from the start date of change process &V3&. The dates have to be
identical for a contract split, however.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Set the same start date for both processes.
Error message extract from SAP system. Copyright SAP SE.
CRM_LEASING_CHANGE162
- Different start date for contract split ?The SAP error message CRM_LEASING_CHANGE162 indicates that there is a discrepancy in the start dates when attempting to split a leasing contract. This error typically arises in the context of contract management within the SAP Customer Relationship Management (CRM) module, particularly when dealing with leasing contracts.
Cause: The error occurs when: You are trying to split a leasing contract, but the start dates of the resulting contracts do not align correctly. The system expects the start date of the new contract(s) to be the same as the original contract or to follow a specific sequence, but the provided dates do not meet these criteria.
Solution: To resolve this error, you can take the following steps: Check Contract Dates: Review the start dates of the original contract and the proposed split contracts. Ensure that the start dates are consistent and valid according to the business rules defined in your system. Adjust Start Dates: If the start dates are incorrect,
Get instant SAP help. Sign up for our Free Essentials Plan.
CRM_LEASING_CHANGE161
Term not possible; the old end of lease must be retained
What causes this issue? You specified &V2& &V3& as the term for change process number &V1& at item level. With the specified ...
CRM_LEASING_CHANGE160
Check links with other items
What causes this issue? According to the Customizing settings, change process &V3& with number &V1& at item level cannot be linked wi...
CRM_LEASING_CHANGE163
This change process is intended for internal use only
What causes this issue? The system cannot execute change process number &V2& at item level. Change process &V1& is only used internal...
CRM_LEASING_CHANGE164
The change process can only be applied to new contracts
What causes this issue? You cannot execute change process number &V2& at item level. Change process &V1& can only be executed for new...