Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 570
Message text: No activities. Scheduling was not carried out.
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CJ570
- No activities. Scheduling was not carried out. ?The SAP error message CJ570: No activities. Scheduling was not carried out. typically occurs in the context of project management within SAP, particularly when dealing with project structures and activities in the Project System (PS) module. This error indicates that there are no activities available for scheduling in the specified project or work breakdown structure (WBS) element.
Causes:
- No Activities Defined: The most common cause is that there are no activities assigned to the project or WBS element you are trying to schedule.
- Incorrect Project Structure: The project structure may not be set up correctly, leading to a lack of activities.
- Status of Activities: Activities may be in a status that prevents them from being scheduled (e.g., they are marked as "deleted" or "not released").
- Missing Dependencies: If activities are dependent on other activities that are not defined or are not in a proper status, scheduling may not occur.
- Incorrect Selection Criteria: The selection criteria used for scheduling may not match any existing activities.
Solutions:
- Check Activity Assignment: Ensure that activities are properly defined and assigned to the project or WBS element. You can do this by navigating to the project in the Project Builder (CJ20N) and checking the activities.
- Review Project Structure: Verify that the project structure is correctly set up and that all necessary components are included.
- Check Activity Status: Ensure that the activities are in a status that allows them to be scheduled. Activities should be released and not marked for deletion.
- Define Dependencies: If there are dependencies between activities, ensure that they are correctly defined and that all prerequisite activities are available.
- Use Correct Selection Criteria: When attempting to schedule, ensure that the selection criteria you are using are appropriate and that they match the activities you expect to schedule.
- Recreate Activities: If activities are missing or incorrectly set up, consider recreating them to ensure they are properly configured.
Related Information:
If the issue persists after checking these aspects, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in the Project System module.
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ569
Project structure contains several calendars
What causes this issue? You have entered different factory calendars for the dates of the individual WBS elements. You could get dates for the WBS el...
CJ568
WBS element &1: Activity &2 in network &3 is not in time frame
What causes this issue? Activity &V2& in network &V3& no longer lies within the time frame of WBS element &V1&.How to fix thi...
CJ571
No actual dates could be determined for WBS element &
What causes this issue? You cannot copy.System Response The system issues an error message and will not allow you to continue with this transaction ...
CJ572
Subnetwork cannot be shown
What causes this issue? You selected an activity and want to show its dependent subnetwork.System Response The subnetwork for the selected activity ...
Click on this link to search all SAP messages.